Sunday 5 August 2018

Whether Arbitrator has power to Award interest unless specifically barred from awarding?

The
present case must be decided on the general rule that an arbitrator
has the power to award interest unless specifically barred from
awarding it; and the bar must be clear and specific.

Relying on the three Judge Bench judgment in Union of India v.
Ambica Construction (supra) and in Irrigation Deptt., State of Orissa
(supra), this Court held that the bar to award interest on the amounts
payable under the contract would not be sufficient to deny the
payment of interest pendente lite.

18. Thus when a dispute is referred to for adjudication to an
arbitrator, a term of such a nature as contained in the Clause 16(3) of
GCC, that is binding on the parties cannot be extended to bind an
Arbitrator. The Arbitrator has the power to award interest pendente lite

REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL Nos. 5964-5965 OF 2018
[Arising out of SLP (CIVIL) Nos. 3310-3311 of 2016]

M/s Raveechee and Co. Union of India .

S.A. BOBDE, J.
Dated:JULY 03, 2018

1. Leave granted.
2. These Civil Appeals arise out of the final judgment and order of
Gujarat High Court dated 23.07.2015 in F.A No 189 of 2005 and the
final judgment and order dated 5.11.2015 in MCA No 3178 of 2015 in
F.A No 189 of 2005. The High Court partly allowed the appeal of the
Respondent- Union of India and quashed Order of the Arbitrators and
set aside the amount awarded by them in respect of Claim No 12. The
Arbitrators, under Claim No. 12 awarded interest pendente lite at 12%
on the award of Rs. 30 lacs excluding security deposits amounting to
1
Rs. 44,92,800/- per annum from 26.09.1988 to 22.03.2001. Further,
the High Court dismissed the review application filed by the appellant.
3. The appellant – M/s Raveechee and Co. and the respondent-
Union of India entered into a contract dated 02.06.1981 for quarrying,
stacking and loading stone ballast, broken stone aggregate, rubble etc.
from the Western Railway quarry at Udvada at an estimated cost of Rs.
55,81,000/. Thereafter, disputes arose between the parties due to
which the appellant called upon the General Manager, Western Railway
to appoint Arbitrators in order to settle the dispute. The Arbitration
proceedings commenced on 26.09.1988 and the award was passed on
22.03.2001.
4. The Arbitral Tribunal comprising of Shri N.K. Gupta, Chief
Engineer (C&S) and Shri R.K. Sinha, Director, Finance, KRCL, awarded a
total of Rs. 76,43,800/- as against the claim of Rs. 1,34,87,044/- raised
by the appellant. An award for the Claim Nos. 1-12 raised by the
appellant was made. The present dispute relates to the amount
awarded under Claim No. 12 i.e. Interest. The Arbitrators awarded the
appellant interest pendente lite at 12% on the award for damages
excluding security deposits amounting to Rs. 44,92,800/- from
26.09.1988 to 22.03.2001.
5. The appellant thereafter filed a Civil Miscellaneous Application
No.22 of 2001 along with the award dated 22.03.2001 in the Civil
Court. The award was made a rule of the Court by an order dated
2
29.07.2004 under Section 17 of the Arbitration Act of 1940 (hereinafter
referred to as ‘the Act’) by the Civil Court. The respondent challenged
the order of the Civil Court dated 29.07.2004 in appeal. The High
Court partly allowed the appeal and set aside the order of Arbitrators
qua Claim No.12 under which the Arbitrators had awarded Rs.
44,92,800/- as interest pendente lite. The Arbitrators awarded
amounts in favour of the appellant as follows: Claim No.1 – Rs. 12 lacs,
Claim No.3 – Rs. 8 lacs and Claim No. 5 – Rs. 10 lacs and interest on
the total amount of damages (i.e. Rs. 12 lacs + Rs. 8 lacs + Rs. 10 lacs
= Rs. 30 lacs) excluding the amount of security deposits. Thus, interest
on Rs. 30 lacs from 26.09.1988 to 23.03.2001 at 12 % amounting to
Rs. 44,92,800/-.
6. The appellant, aggrieved by the High Court’s judgment and order
dated 23.07.2015 filed a review application before the High Court. The
High Court dismissed the review application vide judgment and order
dated 05.11.2015. The present SLPs are filed against the High Court
judgments and orders dated 23.07.2015 & 05.11.2015 passed by the
High Court.
7. The question that arises for determination before this Court is:
Whether Clause 16(3) (reproduced hereafter) of the General Contract
Clauses (hereinafter referred to as “GCC”) restricted the power of the
arbitrator to award interest pendente lite?
3
8. In the present case, the Arbitral Tribunal giving effect to the
purport of Clause 16(3) did not award any interest on security deposits.
The clause in terms states that no interest will be payable on earnest
money, security deposits or on any amounts payable to the contractor
under the contract.
The Arbitrators in their award have relied on Clause 16(3) of the
contract to deny interest on the security deposit. The Arbitrators held
that what was intended under Clause 16(3) barred the grant of interest
on earnest money, security deposit and amounts payable to the
appellant, it does not in any way bar grant of interest pendente lite.
9. Clause 16(1) and 16(3), which are relevant, read as follows:
“16(1):- The earnest money deposited by the
contractor with his tender will be retained by the
Railways as part of security for the due and faithful
fulfillment of the contract by the contractor. The
balance to make up the security deposit, the rates
for which are given below, may be deposited by the
contractor in cash or in the form of Government
Securities or may be recovered by percentage
deduction from the contractor’s ‘on account’ bills.
Provide also that in case of defaulting contractor the
Railway may retain any amount due for payment to
the contractor on the pending ‘on account bills’ so
that the amounts so retained may not exceed 10% of
the total value of the contract.
“16(3): No interest will be payable upon the earnest
money and the security deposit or amounts payable
to the Contractor under the Contract, but
Government Securities deposited in terms of sub
clause (1) of this clause will be payable with interest
accrued thereon.”
4
10. On behalf of the Union of India, it is contended that the
Arbitrators by reason of Clause 16(3) could not have awarded interest
pendente lite. This contention is incorrect. Ex facie the clause does not
deal with interest pendente lite. In terms, the clause only bars interest
upon earnest money and security deposits or amounts payable to the
contractor under the contract. The above mentioned amounts are
amounts which in a sense belong to the contractor. They are amounts
voluntarily deposited with the other contracting party in order to be
refunded or forfeited depending on performance of the contract. As
such they are not amounts of which the contractor is deprived the use
of against his wishes, so as to attract interest.
It is not the case of the Government before us that interest has
been awarded to the contractor under any of the three heads. Neither
does any question of interest payable on Government security arise in
the present case. The contention put forth by the Government is that
the above clause in the agreement bars the Arbitrators from awarding
interest pendete lite. On a plain reading we find that there is no such
bar.
11. In fact, the Arbitrators have awarded amounts to the claimant on
account of the losses suffered by them for various reasons, mainly due
to the ban on mining. These amounts are not awarded on account of
any payment due under the contract but are awarded on losses
determined in the course of arbitration or the ‘lis’.
5
A claimant becomes entitled to interest not as compensation for
any damage done but for being kept out of the money due to him.
Obviously, in a case of unascertained damages such as this, the
question of interest would arise upon the ascertainment of the
damages in the course of the lis. Such damages could attract interest
pendente lite for the period from the commencement of the arbitration
to the award.
Thus, the liability for interest pendente lite does not arise from
any term of the contract, or during the terms of the contract, but in the
course of determination by the Arbitrators of the losses or damages
that are due to the claimant. Specifically, the liability to pay interest
pendente lite arises because the claimant has been found entitled to
the damages and has been kept out from those dues due to the
pendency of the arbitration i.e. pendente lite.
12. We are, therefore, of the view that the Arbitrators rightly
awarded interest pendente lite for the period from 26.09.1988 to
23.03.2001 which is the date of the award, on the amounts found due
to the claimant. Undoubtedly, such a power must be considered
inherent in an Arbitrator who also exercises the power to do equity,
unless the agreement expressly bars an Arbitrator from awarding
interest pendente lite. An agreement which bars interest is essentially
an agreement that the parties will not claim interest on specified
amounts. It does not bar an Arbitrator, who is never a party to the
agreement from awarding it.
We are not called upon, in this case, to decide whether parties
can agree that they will not claim interest pendente lite even in respect
of unascertained damages determined in the course of arbitration. The
present case must be decided on the general rule that an arbitrator
has the power to award interest unless specifically barred from
awarding it; and the bar must be clear and specific.
13. In Irrigation Deptt., State of Orissa v. G.C Roy1 this Court
thoroughly considered the question of power of the arbitrator to award
interest pendente lite and held that when the agreement between the
parties does not prohibit grant of interest and where the party claims
interest and that dispute has been referred to an arbitrator, then the
arbitrator does have the power to award interest pendente lite.
14. Subsequently, this Court in the cases of Board of Trustee for the
Port of Calcutta v. Engineers-De-Space Age2 and Madnani Construction
Corporation Pvt. Ltd. v. Union of India and Ors.3 held that according to
the view taken in the case of Irrigation Deptt., State of Orissa (supra),
the arbitrator does have the power to award interest pendente lite.
The Court observed that it essentially depends upon the ouster in each
clause, which means that unless there is an express bar that provides
1 (1992) 1 SCC 508
2 (1996) 1 SCC 516
3 (2010) 1 SCC 549
7
that the arbitrator cannot award interest pendente lite, the grant of
interest pendente lite will predominantly be based on the arbitrator’s
discretion to award the same.
15. In Sayeed Ahmed & Co v. State of Uttar Pradesh and Ors.4, this
Court referred to the decision in Superintending Engineer and Ors. v. B.
Subba Reddy5 and observed thus:
“11. Two more decisions dealing with cases arising
under the Arbitration Act, 1940 require to be noticed.
In Superintending Engineer v. B. Subba Reddy (1999)
4 SCC 423 this Court held that interest for prereference
period can be awarded only if there was an
agreement to that effect or if it was allowable under
the Interest Act, 1978. Therefore, claim for interest
for pre-reference period, which is barred as per the
agreement or under the Interest Act, 1978 could not
be allowed. This Court however held that the
Arbitrator can award interest pendente lite and
future interest.”
16. A three Judge Bench of this Court in the case of Union of India v.
Ambica Construction6 held that the power of an arbitrator to grant
pendente lite interest will depend upon several factors such as;
phraseology used in the agreement clauses conferring power relating
to arbitration, nature of claim and dispute referred to arbitrator, and on
what items power to award interest has been taken away and for which
period. The Court observed:
“34. Thus our answer to the reference is that if
contract expressly bars award of interest pendente
lite, the same cannot be awarded by the Arbitrator.
4 (2009) 12 SCC 26
5 (1999) 4 SCC 423
6 (2016) 6 SCC 36
8
And that the bar to award interest on delayed
payment by itself will not be readily inferred as
express bar to award interest pendente lite by the
Arbitral Tribunal, as ouster of power of the arbitrator
has to be considered on various relevant aspects
referred to in the decisions of this Court , it would be
for the Division Bench to consider the case on
merits.”
17. Further, this Court considered an identical clause in the contract
in the case of Ambica Constructions v. Union of India7, wherein it
observed that the Clause of the GCC did not bar the arbitrator from
awarding interest pendente lite and affirmed the award passed by the
arbitrator. The three Judge Bench of this Court held that the contention
raised by the Union of India based on the Clause of the GCC that the
arbitrator could not award interest pendente lite was not a valid
contention and the arbitrator was completely justified in granting
interest pendente lite.
Relying on the three Judge Bench judgment in Union of India v.
Ambica Construction (supra) and in Irrigation Deptt., State of Orissa
(supra), this Court held that the bar to award interest on the amounts
payable under the contract would not be sufficient to deny the
payment of interest pendente lite.
18. Thus when a dispute is referred to for adjudication to an
arbitrator, a term of such a nature as contained in the Clause 16(3) of
GCC, that is binding on the parties cannot be extended to bind an
Arbitrator. The Arbitrator has the power to award interest pendente lite
7 (2017) 14 SCC 323
9
where justified. We, therefore, set aside the judgment of the High
Court and restore the award passed by the Arbitral Tribunal in respect
of Claim No. 12.
19. Appeals are allowed accordingly.
….………………………………..J.
[ S.A. BOBDE ]
….………………………………..J.
[ L. NAGESWARA RAO ]
NEW DELHI
JULY 03, 2018

Print Page

No comments:

Post a Comment