Monday 13 September 2021

Whether the applicant can claim the benefit of deemed permission for construction if he has not made an application for construction in the prescribed form?

From bare perusal of the provisions contained

in section 44 and 45 of MRTP Act it is clear that

for any person, intending to carry out any

development on any land, it is mandatory to make an

application in writing to the Planning Authority

for permission in the "prescribed form" and unless

the application made is in "the prescribed form",

as contemplated by section 44 of the said Act, in

our opinion, one cannot take benefit of the deeming

provision contained in subsection (5) of section 45

of the said Act and carry out any development,

claiming that there was no communication/ reply

from the Planning Authority within sixty days. In

other words, one can take benefit/ advantage of

deeming provision only if the application for

permission for development was made in the

"prescribed form" and if there was no communication

from the Planning Authority either granting or

refusing permission to the applicant within 60 days

from the date of receipt of his application. When

the statute mandates that one has to apply for

building/ development permission in the prescribed

form, the mandate of the statute has to be duly

observed. {Para 7}


10. From bare perusal of the prescribed form it is

clear that it has to be submitted on Rs.0.20 Stamp

and in the form of notice making the intent clear

to carry out development. It further provides that

the application should be accompanied by nine

documents, mentioned in the prescribed form. Thus,

if the application is in the prescribed form and

submitted along with all the relevant/ necessary

documents, then alone, as observed earlier, one can

claim benefit of the deeming provision. If the

prescribed form is compared with the application

dated 9th August, 2010, submitted by the

Petitioner, it is clear that the application was

not in the prescribed form. Therefor, it was not

open to the petitioner to proceed with the

construction of mobile tower treating the inaction/

silence of the Corporation, insofar as their

application dated 9th August, 2010 is concerned, as

deemed permission. In other words, the petitioners

were not obliged to construct the mobile tower

merely because there was no communication from the

Corporation in response to their application dated

9th August, 2010 within 60 days, treating the same

as deemed permission under subsection (5) of

section 45 of the MRTP Act. In the circumstances,

the challenge to the impugned notice on this ground

fails and rejected as such.

11. The next contention urged by Shri Dixit that

the notice under sections 260 and 478 of the BPMC

Act and under Sections 52 and 54 of the MRTP Act,

is illegal, also deserves to be rejected outright.

Shri Dixit urged that the provisions of Sections

260 and 478 would not apply to the facts of the

present case, since, the petitioner had made an

application for seeking permission for development

under Section 44 of the MRTP Act. We have already

taken a view that application dated 9th August,

2010 for development/ for erecting the mobile

tower, in our opinion, was not an application as

contemplated by Section 44 of the MRTP Act and,

therefore, it was not open to the petitioner to

treat the silence or inaction on the part of the

Corporation for sixty days and proceeded with

construction of the mobile tower.

12. A plain reading of Section 260 of the BPMC Act

shows that the procedure under this provision

presupposes a situation, whereby an application in

the prescribed form, has been made and it has

either been rejected or where the permission

granted has been exceeded or a situation, whereby

deemed permission is pleaded, but is not justified.

The case of the petitioner does not fall in any of

these categories. It is so observed by this Court

in the case of Nanasaheb Nagoji Bhosale (Supra).

Section 478 contemplates an entirely different set

of cases whereby the records of the Corporation

indicate that no application whatsoever was ever

made, and consequently, that it was neither

rejected nor granted nor was there any deemed

permission. In the present case, the application

dated 9th August, 2010 was no application as

contemplated by section 44 of the MRTP Act.

Therefore, there was no occasion for the

Corporation to either reject or to grant and no

reason for the petitioner to treat the silence on

the part of the Corporation as deemed permission.

Section 52 of the MRTP Act provides for penalty for

unauthorised development or for use otherwise than

in conformity with the development plan and section

53 confers power on the planning authority to

remove unauthorized development. A plain reading

of all these provisions, in the light of our

finding that application dated 9th August, 2010 was

not an application for development as contemplated

by section 44 of the MRTP Act, would show that the

Corporation is justified in issuing the impugned

notice against the petitioner.

IN THE HIGH COURT OF JUDICATURE AT BOMBAY, BENCH ATAURANGABAD

APPELLATE SIDE, CIVIL JURISDICTION

WRIT PETITION NO.: 48 OF 2011

GTL Infrastructure Ltd. V/s The Dhule Municipal Corporation and others

CORAM: D. B. BHOSALE AND S. B. DESHMUKH,JJ.

DATED:9th JUNE, 2011.

Citation: 2011(6) BOM CR 152: 2011(6) MHLJ 215

1. Heard learned counsel for the parties. Rule.

Rule, made returnable forthwith and heard finally

with the consent of parties.

2. This writ petition under Article 226 of the

Constitution of India is basically directed against

the notice dated 21st October, 2010 issued by

Respondent No.1 Dhule

Municipal Corporation (for

short, the Corporation) under sections 260 and 478

of the Bombay Provincial Municipal Corporation Act,

1949 (for short, BPMC Act) and section 52 and 53 of

the Maharashtra Regional and Town Planning Act,

1966 (for short, MRTP Act). By this notice,

petitioners are directed to remove/ demolish a

mobile tower/ cellular site within 30 days, which

has been erected/ constructed without permission of

the Corporation.

3. Petitioner is a company incorporated under the

Companies Act, 1956 and is in the business, interalia,

of providing infrastructure services for

erection of mobile towers/ cellular sites. The

petitioners claim that they had applied for


permission for erection of the mobile tower as

provided for under section 44 of the MRTP Act.

Further, it is their case that since the decision

on their application for permission for

development/ construction of mobile tower was not

communicated by the Corporation, either granting

or refusing to grant permission to them, within 60

days from the date of receipt of their application,

they carried out the development treating it as

deemed permission as contemplated by subsection (5)

of section 45 of the MRTP Act and, hence, according

to the petitioners the impugned notice is illegal.

4. The petitioners have also challenged the

resolution passed by the Corporation at ExhibitL

to the writ petition. However, Mr. Dixit, learned

senior counsel did not press this prayer since the

petitioners have an alternate remedy to challenge

the said resolution.

5. Mr. Dixit, learned senior counsel for the

Petitioners addressed the Court only on the

legality of the impugned notice. He contended that

the petitioners had applied for sanction of the

plans and/ or for permission to erect the mobile

tower as contemplated by section 44 of the MRTP Act

and since the Corporation did not communicate its

decision, either granting or refusing permission

within 60 days, the petitioners proceeded to

develop/ construct the mobile tower under the

deeming provision contemplated by subsection (5) of

section 45 of the MRTP Act and, therefore, the

impugned notice cannot be sustained in law and

deserves to be set aside. In support of this

contention, he invited our attention to sections 44

and 45 of the MRTP Act. Then, Mr. Dixit submitted

that the notice under section 260 and 478 of the

BPMC Act is illegal also on the ground that the

petitioners had applied for permission to construct

the mobile tower and, therefore, the Corporation

was not justified in issuing the notice under

section 260 and 478. In other words, he submitted

that in the present case the petitioners had

applied for permission and in view thereof the

impugned notice asking the petitioners to demolish

and/ or remove the mobile tower within 30 days was

illegal. In support of this contention, he placed

reliance upon the judgment of this Court in "Pune

Municipal Corporation, Pune V/s Nanasaheb Nagoji

Bhosale" AIR 1995 Bombay 164.

6. We have perused the provisions of section 44

and 45 of the MRTP Act, so also the provisions of

section 260 and 478 of the BPMC Act. There is no

dispute that construction/ erection of a mobile

tower amounts to "development" within the meaning

of section 2 (7) of the MRTP Act and for its

construction/ erection a permission of the Planning

Authority is necessary as provided for under

section 45 of the said Act. Section 44 of the MRTP

Act provides the procedure for seeking permission

for development. Under this provision, it is

necessary for a person intending to carry out any

development on any land to make an application in

writing to the Planning Authority for permission

"in such form" and containing such particulars and

accompanied by such documents "as may be

prescribed". The form, Appendix A to Bylaw No.6.1

of the Standardised Building Byelaws

and

Development Control Rules for "A" class municipal

councils of Maharashtra, is the prescribed form as

contemplated by section 44 and 45 of the MRTP Act.

Section 45 of the MRTP Act provides that on receipt

of an application, as prescribed under section 44,

the Planning Authority by an order in writing

grants permission with or without conditions or

refuse to grant permission and communicates the

same to the applicant within the prescribed time.

Subsection

(5) of section 45 provides that if the

Planning Authority does not communicate its

decision whether to grant or refuse permission, to

the applicant within 60 days from the date of

receipt of his application, or within 60 days from

the date of receipt of reply from the applicant in

respect of any regulation made by the Planning

Authority, whichever is later, such permission

shall be deemed to have been granted to the

applicant on the date immediately following the

date of expiry of 60 days. Provided that the

development proposal, for which the permission was

applied for, is strictly in conformity with the

requirements of all the relevant Development

Control Regulations framed under this Act or byelaws

or regulations framed in this behalf under any

law for the time being in force and the same in no

way violates either the provisions of any draft or

final plan or proposals published by means of

notice, submitted for sanction under this Act. It

further provides that any development carried out

in pursuance of such deemed permission which is in

contravention of the provisions of the first

proviso, shall be deemed to be an unauthorised

development for the purposes of section 52 to 57 of

the said Act.

7. From bare perusal of the provisions contained

in section 44 and 45 of MRTP Act it is clear that

for any person, intending to carry out any

development on any land, it is mandatory to make an

application in writing to the Planning Authority

for permission in the "prescribed form" and unless

the application made is in "the prescribed form",

as contemplated by section 44 of the said Act, in

our opinion, one cannot take benefit of the deeming

provision contained in subsection (5) of section 45

of the said Act and carry out any development,

claiming that there was no communication/ reply

from the Planning Authority within sixty days. In

other words, one can take benefit/ advantage of

deeming provision only if the application for

permission for development was made in the

"prescribed form" and if there was no communication

from the Planning Authority either granting or

refusing permission to the applicant within 60 days

from the date of receipt of his application. When

the statute mandates that one has to apply for

building/ development permission in the prescribed

form, the mandate of the statute has to be duly

observed.

8. In the present case, we have perused the

application dated 9th August, 2010 made by the

petitioners, which according to Mr. Dixit, is under

section 44 of the MRTP Act. It is at ExhibitG

to

the writ petition. It would be relevant to

reproduce the said application to find out whether

it was made in the prescribed form:

"EXH.G

G T L

INFRASTRUCTURE Date: 9.8.10.

To,

The Commissioner,

Dhule Municipal Corporation,

Dhule, Dist. Dhule.

Ref. Our application letter for noc dated 14

July 2010.

1. We are a company registered under the

Companies Act, 1956. We are a proper license

holder of IP 1 issued by Department of Tele

communication, New Delhi and engaged in the

business of installation of passive

infrastructure in the telecom circle of

Maharashtra and Goa.

2. We are required to erect mobile towers on

rooftop of buildings and ground base tower,

after entering into a proper agreement with the

owners.

3. We are required to erect mobile towers on

the roof top of the buildings & ground based

tower after entering into a proper agreement

with owners. We have entered into a License

Agreement with Kashinath Babulal Chaudhari, the

owner of the property Plot No. 3/

A, P. No.

200/4, Survey NO.546, 80 feet Road, Dhule Tal.

& Dist. Dhule. Mentioned here in above for

erection of mobile tower.

4. We had applied for your Permission for

installation of mobile tower on the above said

property on 14th July, 2010.

5. Therefore, as per your directions, we are

resubmitting all the below mentioned requisite

docs in the prescribed format for your record

purpose on time to time as per your

requirements in office by hand through our

representative.

i. License Agreement.

ii. Tower Drawing 3 copies.

iii. Structural stability certificate.

iv. 7/12 3stract.

v. Building permission.

vi. Sanction Plan.

vii. Municipal tax paid receipt.

viii.Consent letter from owner on Rs.100

Stamp

ix. other requisite documents as per your

instructions.

We further request you to issue no objection

certificate for our previously mentioned

installation at the earliest.

Kindly Acknowledge receipt and oblige.

For GTL Infrastructure Limited.

Sd/Authorized

Singature.

GLOBAL Group Enterprise Sd/9.,

8.10

Site Name: Malegaon GTL Infrastructure Limited

(Aircel) Global House | Lane No.15,

Prabhat Road, Erandwane |

Pune 411 004 | India

Tel:+91 20 25650708

FAX: + 91 2025659713

9. At this stage, it would also be advantageous

to reproduce the prescribed form [Appendix A] to

consider whether the application dated 9th August,

2010 (ExhibitG)

was in the prescribed form.

APPENDIX A

(Byelaw

No. 6.1)

Form for first Application for development

and to erect a building.

(Under section 44/45/58/59 of Maharashtra

Regional and Town Planning Act, 1966 and

under Section 189/ 190/ 191/ 192 of

Maharashtra Municipalities Act, 1965)

(On Rs. 0.20 Stamp)

To,

The Authority,

Municipal Council of Sir,

I hereby give notice that I intend to

carry out development in the site/ to

erect to reerect/

to demolish/ to make

material alteration in the

building .................................


.............. on/ in Plot

No. ........................, land, Town

and, Revenue Survey No. .............

C.T.S. No. ........................

situated at Road/ Street ................

City ......

I forward herewith the following

plans and statements (Item 1 to 6) in

quadruplicate, wherever applicable, signed

by me and (Name in block

letters) ..................... the

lincesed Architect/ Engineering/

Structural Engineer/ Supervisor Licence

No. ...................... who have

prepared the plans, designs and a copy of

other statements/ documents/ as applicable

Items 1 to 9):

1. Key Plan (Location) Plan.

2. Site Plan

3. Subdivis9ion

Layout Plan.

4. Building Plan.

5. Services Plan.

6. Particulars of development in

Form.

7. Ownership Title.

8. Attested copy of Receipt for

Payment of

Application fee.

9. Clearance Certificate of TAX

Arrears.

I request that the proposed

development/ construction may be approved

and permission accorded to me to execute

the work.

Signature of Owner ...............

Name of Owner ...................

Address of Owner ............

Date ...................... ..........."

10. From bare perusal of the prescribed form it is

clear that it has to be submitted on Rs.0.20 Stamp

and in the form of notice making the intent clear

to carry out development. It further provides that

the application should be accompanied by nine

documents, mentioned in the prescribed form. Thus,

if the application is in the prescribed form and

submitted along with all the relevant/ necessary

documents, then alone, as observed earlier, one can

claim benefit of the deeming provision. If the

prescribed form is compared with the application

dated 9th August, 2010, submitted by the

Petitioner, it is clear that the application was

not in the prescribed form. Therefor, it was not

open to the petitioner to proceed with the

construction of mobile tower treating the inaction/

silence of the Corporation, insofar as their

application dated 9th August, 2010 is concerned, as

deemed permission. In other words, the petitioners

were not obliged to construct the mobile tower

merely because there was no communication from the

Corporation in response to their application dated

9th August, 2010 within 60 days, treating the same

as deemed permission under subsection (5) of

section 45 of the MRTP Act. In the circumstances,

the challenge to the impugned notice on this ground

fails and rejected as such.

11. The next contention urged by Shri Dixit that

the notice under sections 260 and 478 of the BPMC

Act and under Sections 52 and 54 of the MRTP Act,

is illegal, also deserves to be rejected outright.

Shri Dixit urged that the provisions of Sections

260 and 478 would not apply to the facts of the

present case, since, the petitioner had made an

application for seeking permission for development

under Section 44 of the MRTP Act. We have already

taken a view that application dated 9th August,

2010 for development/ for erecting the mobile

tower, in our opinion, was not an application as

contemplated by Section 44 of the MRTP Act and,

therefore, it was not open to the petitioner to

treat the silence or inaction on the part of the

Corporation for sixty days and proceeded with

construction of the mobile tower.

12. A plain reading of Section 260 of the BPMC Act

shows that the procedure under this provision

presupposes a situation, whereby an application in

the prescribed form, has been made and it has

either been rejected or where the permission

granted has been exceeded or a situation, whereby

deemed permission is pleaded, but is not justified.

The case of the petitioner does not fall in any of

these categories. It is so observed by this Court

in the case of Nanasaheb Nagoji Bhosale (Supra).

Section 478 contemplates an entirely different set

of cases whereby the records of the Corporation

indicate that no application whatsoever was ever

made, and consequently, that it was neither

rejected nor granted nor was there any deemed

permission. In the present case, the application

dated 9th August, 2010 was no application as

contemplated by section 44 of the MRTP Act.

Therefore, there was no occasion for the

Corporation to either reject or to grant and no

reason for the petitioner to treat the silence on

the part of the Corporation as deemed permission.

Section 52 of the MRTP Act provides for penalty for

unauthorised development or for use otherwise than

in conformity with the development plan and section

53 confers power on the planning authority to

remove unauthorized development. A plain reading

of all these provisions, in the light of our

finding that application dated 9th August, 2010 was

not an application for development as contemplated

by section 44 of the MRTP Act, would show that the

Corporation is justified in issuing the impugned

notice against the petitioner.

13. The judgment of this Court in Nanasaheb Nagoji

Bhosale's case (supra) relied upon by the

Petitioner, in our opinion, is of no avail to the

petitioner in view of the finding recorded in the

foregoing paragraphs in respect of petitioner's

application under section 44 of the MRTP Act dated

9th August, 2010. Thus, the Challenge to the

impugned notice fails on this ground also.

14. In the result, Writ petition is dismissed.

Rule is discharge. No costs.

15. However, dismissal of the petition shall not

preclude the petitioner from making an application

to the Corporation for regularisation of the mobile

tower. If any such application is made by the

petitioner, the Corporation, while dealing with the

same, shall consider whether the mobile tower is in

conformity with the requirements of all the

relevant development control rules or byelaws

or

regulations framed in this behalf under any law for

the time being in force and the same in no way

violates either the provisions of any draft or

final plan or proposals published by means of

notice submitted for sanction under the MRTP Act.

[S. B. DESHMUKH, J.] [D. B. BHOSALE, J.]

Dated:09/06/2011.


Print Page

No comments:

Post a Comment