Sunday 12 September 2021

Whether high court can entertain a writ petition on the disputed questions of fact in respect of contractual matters?

 Therefore, the dispute could not be raised by way of a writ petition on the disputed questions of fact. Though, the jurisdiction of the High Court is wide but in respect of pure contractual matters in the field of private law, having no statutory flavour, are better adjudicated upon by the forum agreed to by the parties. The dispute as to whether the amount is payable or not and/or how much amount is payable are disputed questions of facts. There is no admission on the part of the appellants to infer that the amount stands crystallized. Therefore, in the absence of any acceptance of

Joint Survey Report by the competent authority, no right would

accrue to the writ petitioner only because measurements cannot

be undertaken after passage of time. Maybe, the resurvey cannot

take place but the measurement books of the work executed from

time to time would form a reasonable basis for assessing the

amount due and payable to the writ petitioner, but such process

could be undertaken only by the agreed forum i.e., arbitration and not by the Writ Court as it does not have the expertise in respect of  measurements or construction of roads.

 REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 4981 OF 2021


UNION OF INDIA & ORS.  Vs  M/S PUNA HINDA 

Author: HEMANT GUPTA, J.

Dated: SEPTEMBER 6, 2021.


1. The challenge in the present appeal is to an order dated

17.11.2017 passed by the Division Bench of the Gauhati High Court

dismissing an intra-court appeal and affirming the order passed by

the learned Single Bench on 4.8.2016.

2. The learned Single Bench of the High Court allowed the writ

petition filed by the respondent – M/s. Puna Hinda1 who had sought

quashing of letters dated 27.8.2015 and 21.10.2015 and also a

direction to pay Rs. 31,57,16,134/- with interest at the rate of 18%

p.a.

3. The learned Single Judge held that payment in terms of Final Joint

Survey/Measurement Report dated 24.10.2013 be taken into

consideration for making revised Detailed Project Report (DPR) and

1 Hereinafter referred to as the ‘writ petitioner’

thus passed necessary orders for payment of the amount due to

the writ petitioner within four months of the receipt of copy of the

order. In an appeal filed by the appellants, the Division Bench of

the High Court held that resurvey for measurement and DPR would

not be just and fair at this stage since five monsoons had passed.

Therefore, the only option left to the appellants was to approve the

DPR and pay the pending bills on the basis of Final Joint

Survey/Measurement Report dated 24.10.2013.

4. Brief facts leading to the present appeal is that a Notice Inviting

Tender (NIT) was issued on 22.10.2008 for construction and

improvement of road from 26.800 km to 47.850 km between Lumla

and Tashigong under Special Accelerated Rural Development

Programme (SARDP). The bid of the writ petitioner was accepted

at Rs.31,87,58,950/-. The work order was issued on 15.7.2009.

The said work order was amended by the parties on 15.3.2012

leading to enhanced work cost at Rs. 35,03,15,695.23. The work

order had provided details of the work to be carried out and the

estimated amount payable for each work with rate of each work.

The work was divided into three parts, such as, Formation work,

which included jungle clearance etc.; Permanent work which

included excavation in trenches, cement concrete; and Surface

work which included preparation of subgrade in soil mix boulder,

laying, spreading and compacting graded stone aggregate. The

measurement process for payment was specified in the General

Conditions of Contract, which read as under:

“2 .8 .1 Excavation for roadway shall be measured by taking

cross Section at suitable intervals in the original position before

the work starts and after its completion and computing the

volumes in cum by the method of average and areas for each

class of material encountered. Where it is not feasible to

computes volumes by this method because of erratic location of

isolated deposits, the volumes shall be computed by other

accepted methods.

2.8.2 At the option of the Engineer-In-Charge/QC Contract, the

Contractor shall leave depth indicators during excavations of

such shape and size and in such positions as directed so as to

indicates the originals ground level as accurately as possible.

The Contractor shall see that there remain intact till the final

measurements are taken.”

5. The contractor completed the formation work by 20.9.2012,

the communication of which was sent by the writ petitioner

on 17.10.2012. The joint survey of the works was carried out

by the Board of Officers on 23.1.2013. The Board of officers

made the following recommendations: -

“RECOMMENDATION OF THE BOARD

FORMATION WORKS

20. The details of items of formation works provisioned (as

per DPR), executed departmentally and balance between

Km 26.800 and Km 31.00 are as under:

xx xx xx

21. The details of items of formation works provisioned in

DPR and as arrived at after detailed Joint Survey from Km

31.000 to Km 47.850 are as under:

Location In SMB

(cum)

In SR

(cum)

In HR

(cum)

Embankment

filing (cum)

Jungle

Clearance

(10 Sq m)

Km 31.000-Km 47.850

(a) Qty of

Fmn works

provisioned

as per dpr

633835.33 15298.87 81438.22 0.00 25275.00


(b) Qty of

Fmn works

as per joint

survey

356166.00 182073.00 337447.00 0.00 23123.00

The quantities as arrived at after joint survey are

theoretical only and after completion of formation works

Total station survey shall be carried out as per Clause 18 of

Special Conditions of Contract to ascertain the actual

quantity executed. Hence these quantities be treated as

accurate, based on theoretical calculations.

The classification of soils as shown in joint survey are

based on visual appearance of soil strata. The actual

classification of excavation shall be decided during

execution by Engg in Charge and OC Contract as per clause

2.2.2 of Particular specification of CA at page no. 87 duly

supported with photographs.

The quantities of formation works as arrived at after

joint survey between Km 26.800 and Km 47.850 as per

details given at Appendix ‘A’ are recommended for

execution of ground and will form the basis of RAR payments

to be made as per Contract Provision/Stipulation during

execution of works under CA No. CE/VTK/03/2009-10. The

final quantity shall be arrived only after completions of

formation works by carrying out Total station survey. Hence,

amendment in quantities of formation works is

recommended only after final joint survey on completion of

work.

22. Unlined drain of any shape cut to the required

gradient with average sectional area 0.50 Sqm in soft rock –

2299.80 Mtrs and in Hard rock-5146.00 Mtrs as arrived at

after Joint Survey are recommended for construction on

ground between Km 26.800 to Km 47.850 under CA No.

CE/VTK/03/2009-10.

PERMANENT WORKS

23. Abstract of quantity of item of works for construction of

permanent structures which are executed and balance

between Km 26.800 and Km 31.000 and structures

provisioned between Km 31.000 and Km 47.850 has been

worked out and shown at Appendix ‘B’.

24. Permanent works to be executed under CA No. CE/VTK/

03/2009-10 are as under:

(a) R/Wall: R/Walls balance between Km 26.800 and Km

31.000 and provisioned between Km 31.000 and Km

40.000 at locations mentioned in Annexure-I to

Appendix ‘B’ are recommended for execution on

ground under CA No. CE/VTK/03/2009-10.

(b) RCC Culverts: RCC Culverts balance between Km

26.800 and Km 31.000 including two incomplete RCC

culverts at locations Km 28.300 and Km 29.000 and

those provisioned between Km 31.000 and Km 47.850

at locations mentioned in Annexure-II to Appendix “B”

are recommended for execution on ground under CA

No. CE/VTK/03/2009-10.

(c) T/Walls Below RCC Culverts: T/Walls below RCC

Culverts balance between Km 26.800 and Km 31.000

and those provisioned between Km 31.000 and Km

47.850 at locations mentioned in Annexure-III to

Appendix ‘B’ are recommended for execution on

ground under CA No. CE/VTK/03/2009-10.

(d) T/Walls below R/Walls: T/Walls below R/Walls

provisioned between Km 26.800 to Km 31.000 and

Km 31.000 to Km 47.850 at locations mentioned in

Annexure IV to Appendix ‘B’ are recommended for

execution on ground under CA No. CE/VTK/03/2009-

10.

(e) Breast Walls: Breast Walls provisioned between Km

26.800 to Km 31.000 and between Km 31.000 to Km

47.850 at locations mentioned in Annexure V to

Appendix ‘B’ are recommended for execution on

ground under CA No. CE/VTK/03/2009-10.

(f) Lined drain: Lined drain for 13271.00 Mtr length of

trapezoidal shape in plum concrete between Km

26.800 and Km 47.850 at locations as arrived at after

Joint Survey and mentioned at Annexure-VI to

Appendix ‘B’ are recommended for execution on

ground under CA No. CE/VTK/03/2009-10.

(g) Road Furniture: Road furniture provisioned between

Km 26.800 and Km 47.850 as per Annexure-VII to

Appendix ‘B’ are recommended for providing/fixing on

ground under CA No. CE/VTK/03/2009-10.

25. Working drawings of all permanent structures (different

sizes/types) are enclosed with this Board of Officers.

26. Construction of permanent structures at designated

locations or otherwise will only be executed after obtaining

prior approval of Engineer-in-Charge/OC Contract as per

ground requirement.

27. The quantity of items of Permanent works as arrived at

after Joint Survey between Km 26.800 and Km 47.850 as per

details given at Table-2 of Appendix ‘B’ are recommended

for execution on ground and will form the basis of RAR

payments to be made as per Contract Provision/Stipulation

during execution of works under CA No. CE/VTK/03/2009-10.

Amendment in quantities of permanent works is

recommended only during final stage of completion of

permanent works.

SURFACING WORKS

28. No surfacing works has been executed departmentally

between Km 26.800 and Km 47.850. Quantities of various

items of surfacing works as arrived at after Joint Survey as

per details given at Appendix ‘D’ are recommended for

execution on ground under CA No. CE/VTK/03/2009-10.

SUMMARY OF PAVEMENT WORKS AS PER JOINT SVY

Sl.

No.

Items of

Surfacing

A/U Total

Quantity

Surfacing Eqvt

DGBR CL-9

1 Preparation of

subgrade in SMB

Sqm 82943.75 0.00

2 Preparation of

subgrade in SR

Sqm 14373.75 0.00

3 Preparation of

subgrade in HR

Sqm 21227.21 0.00

4 Sand Blanketting

25mm

Sqm 21227.21 0.00

5 GSB 150mm thick Sqm 97317.50 5.90

6 GSB 100mm thick Sqm 64229.50 2.60

7 WMM 75mm thick Sqm 256370.31 15.54

8 Prime coat over

WMM surface

Sqm 85456.71 0.00

9 BM 50mm thick Sqm 85456.71 10.36

10 SDBC 25mm thick Sqm 85456.71 5.18

Total Surfacing Km Eqvt Cl-9 39.58

29. However, if the soil classification varies from the

enclosed strata as shown in (Annexure-I to Appx “C”), layer

combination shall be revised accordingly and be executed

after prior approval of OC Contract duly supported with

photographs of Soil strata.

30. Amendment in quantities of surfacing works are

recommended only during final stage of completion of

surfacing works.

xx xx xx

CE/VTK/03/2009-10 ON ROAD LUMLA-TASHIGONG BETWEEN

KM 26.800 TO KM 47.850

Sl.

No.

Location Earth Work involved in

CUM

Earth

work in

Embankment

Jungle

Clearance

Unlined

Drain in

SR (M)

Unlined

Drain in

From To Cutting HR(M)

SMB SR HR

1 26.800 31.0

00

1872

7.01

1735.04 7631. 42 0.00 0 125.00 217.80

2 31.000 47.8

50

35616

6.00

182073.

00

337447.0

0

0.00 23123.0 2174.8

0

4928

Presiding Officer Lt Col Dhiraj Minotra, OC, 117 RCC

(GREF) OC Contract

Member 1 Sd/- (Comments KS, AE(Civil) Eng-in-

Charge

117 RCC (GREF)

2 Shri __________A Holder Authorized rep of M/s

Puna Hinda

6. The writ petitioner was directed not to cut extra road formation

width without obtaining proper written permission from the

Competent Authority on 28.1.2013, and in case any formation work

was carried out, no payment shall be made after the report of the

Board of Officers.

7. The Second in Command of the Unit sought approval of the

Headquarters on 24.10.2013 after the joint survey of formation

cutting was done by the Joint Survey Team. It is the said Joint

Survey Report which was rejected by the Competent Authority at

the Headquarter, when the following communication was

addressed to the field office with a copy to the writ petitioner. The

said communication of the Commissioner on 29.10.2013 reads as

under:

“Headquarters

763 Boarder Roads Task Force

Pin-930763

C/O 99 APO

8001/715/EB

29 Oct 2013

117 RCC (GREF)

PIN 9300117

C/O 99 APO

CONSTRUCTION AND IMPROVEMENT OF ROAD LUMLA

TASHIGONG FROM KM 26.800 TO 47.800 SINGLE LANE

STANDARD UNDER PHASE ‘A’ OF SARDP INE IN TWANG

DISTT OF ARUNACHAL PRADESH:CA NO. CE(P) VTK/03/2009-

10

Refer your letter No. 804/vtk/03/2009-10/79 dated 24 Oct

2013.

2. The documents namely base plan, details of curves and

quantity calculations and cross sections have been

scrutinized and found that they are not in order.

3. Table 6.10 of hill road manual IRC:SP:46-1998 at Page No.

40 is not correctly interpreted and marked on cross section.

Minimum sight distance ‘m’ (P1 ref to sketch 6.1) at Page

No. 40 of hill road manual IRC SP.46-1996 is to be measured

from centre line of carriage way and not from the edge of

the road way.

4.Hence, the above documents have not been approved by

competent authority and cancelled herewith.

Sd/-

(MANV Prasad)

SE (Civ)

Commissioner

Copy to

M/S Puna Hinda,

C/O Time Video Library

Akash Deep Market Ganga

Pot Itanagar Distt. Papum Pare

Arunachal Pradesh Pin-791111.”

8. The writ petitioner was informed vide letter dated 24.3.2014 to

provide a breakup of the contract agreement amount of Rs.31.87

crores and also point out that initial joint survey was carried out by

a team comprising of then OC Contract, Engineer-In-charge, JE Incharge

of contract and Contractor to assess the actual quantities of

earth work before commencement of the work on ground. A

comparison of the contract amounts as well as amended contract

amount was delineated in Table 3 which reads as thus:

S. No. Description Original CA

Amount (Crs)

Amended

CA Amount

(Crs)

Variation

/o/ \(/o)

1 Formation works Rs.11,98 Rs.16.27 + 35,81

2 Permanent works Rs.06.63 Rs.6.25 -05,73

3 Surfacing works Rs.13.26 Rs.12.51 -05,6.6

Total Rs.31.87 Rs.35.03 +09.91

9. It was also pointed out that the formation work was completed on

20.9.2012 i.e., not four years back but two years back, as stated by

the writ petitioner. The writ petitioner was communicated that the

unpaid amount on account of original formation work was

Rs.74,33,631/- and Rs.4 crores (approx.) for extra widening of road

beyond 7.45 m. It was communicated as under:

“….

(h) It is worth mentioning that vide your letter No. NCUBRO/

L-T/ADM/2013 dated 12 Jul 2013 (copy enclosed as Appx ‘D’)

you claimed unpaid amount just Rs.74,33,631.00 on account

of original formation work and Rs. 4.00 Crores

(approximately) on account of extra widening of road

beyond 7.45m which is beyond the scope of the contract

and the same has already been intimated to you vide this

HQ letter No. 80914/L-T/26-47/114/E8 dated 19 Aug 2013, in

case you have any approval of the dept for doing-extra work

or if there is any amendment to work order, the same may

please be forwarded for our perusal.

3. In view of the above, it is submitted that each payment

has been released to you as per claim based on joint

measurement and duly accepted by you till finalization of

the formations work as per clause No 18(vi) of special

conditions of contract at serially page 72 of contract

agreement. Hence any extra claim after fifteen months of

completion of formation work is baseless not correct.”

10. The writ petitioner communicated on 12.7.2013 that it would be

bound to stop/abandon the project work and the responsibility shall

be that of the department itself for projecting an indifferent

attitude, if the department cannot pay the work done by it as has

been claimed. It was also asserted that the department may take

over the remaining work and complete it themselves. The amount

claimed in the said letter was as under:

Unseen expenditure done on works

I Land slide clearance

during rainy season

Rs.2500000 x 4 years

Rs.10000000/-

II Earth filling on shoulders

of the road without items

on Boo

Rs.3000000/-

III Local villagers donation for

smooth progress of the

work

Rs.50000000/-

IV Bank Interest due to delay

in payment (Ref RAR Bill)

Rs.1200000/-

V Total Rs30000000/-

11. The writ petitioner submitted a final bill on 17.6.2014 and claimed

a sum of Rs.23,68,11,589.02. It was asserted therein that payment

for amount claimed in the 18 running bills has been made, but in

respect of 19th and 20th running bill, entries have been made in the

measurement book however the payment has not been cleared

yet. The final bill submitted by the writ petitioner was returned

unactioned on 10.8.2014. The writ petitioner was informed that the

payment up to 18 running bills had already exceeded the

permissible approved amount including escalation payment and

was also informed of the following deficiencies:

“3. Also, the following queries/disputes have to be resolved

for finalization of the payment to be made through final bill:-

(a) Supporting documents to the final bill submitted by

you on 17 Jun 2014 are not found enclosed.

(b) Documents as asked vide our letter No. 604/CE/VTK/

03.2009-10 189/E8 dated 02 Aug 2014 have not been

submitted by you.

(c) Claims for extra work done in respect of earth work

quantities beyond scope of contract claimed through

your various letters have been refuted by accepting

officer in this connection please refer HQ CE(P) Vartak

letter No. 80914/L-T/26.800 to 47.850/326/E8 dated

18 Jul 2014 (copy enclosed).

(d) Joint survey earned out in respect of formation works

completed against subject CA is under scrutiny and

not yet approved by competent Financial authority.

(e) Query in respect of escalation payment made against

formation works has been raised by HQ CE(P) Vartak

to HQ DGBR vide their letter No. 80914/L-T/26.800 to

47 85/286/E8 dated 28 Jun 2014 whose reply is

awaited.

(f) As per directions received vide Par 8 of HQ DGBR/ADG

Sectt letter No 71004/DGBR/25/ADG Sectt dated 25

Jul 2014 and HQ CE(P) Vartak letter No B0914/LT/

26.800 to 47.85/341/E8 dated 30 Jul 2014 (copy of

both letters enclosed) recovery of amount on account

of non hancing over the quantity of hard rock from the

formation works executed has to be incorporated in

your final bill on receipt of reply from HQ CE(P) Vartak.

(g) Already matter in respect of disputes relating to

subject CA is with HQ DGBR.”

12. An inter-departmental communication was sent to Head Quarters of

Seema Sadak Bhawan (Border Road Office) on 17.4.2015 that

Board of Officers were not required to be appointed and Accepting

Officer may take the requisite decision. In the status report under

Appendix ‘A’ to the Head Quarter vide letter dated 26.5.2015, it

was noted as under:

“6. From the above it is evident that “work claimed to have

been executed” is much beyond “work ordered to the

contractor”. Moreover the “excess work claimed to have

been executed” by the contractor has not been ordered by

Accepting Officer or Commander of work or Officer

Commanding or Engineer-in-Charge.

7. The “Joint Survey Report” on the basis of which

contractor is asking additional payment has not been

authenticated/admitted by the Chief Engineer(P) Vartak nor

ordered by any authority. Therefore contractually

contractor’s claim cannot be admitted.

8.All payments correctly due to contractor have been

already made.”

13. The terms of reference of the Board of Officers were determined on

22.7.2015, with copy of the letter to the writ petitioner, as under:

“3. Terms of References of the Board of Officers will be as

under:

(a) To carry out Joint Survey with Tetal Station from KM

26.800 to 47.852 on Lumla-Tashigong road.

(b) To plot the Cross Section at suitable interval and

Longitudinal Section with Corresponding RL.

(c) To ascertain whether any extra work or account of

Berm filing/shoulder or curves has been done.

(d) To measure the exact length and width of road after

formation cutting.”

14. The writ petitioner objected to the constitution of the Board of

Officers on 12.8.2015 and claimed a sum of Rs.23,68,11,589/-,

breakup of which has been reproduced hereunder. The said claim

was refuted by the appellants vide communication dated

27.8.2015. The constitution of the Board of Officers was cancelled

on 8.6.2015.

I Formation Work Rs.28,55,94,528.95

Total paid amounts [RAR Bills for

formation

cutting]

Rs. 16,24,41,060.00

Balance amounts Rs. 12,27,52,095.34

II For curve improvement [as per Hill

Road Manual]

Rs.4,51,04,271.98

III For earth filling on shoulder of road

[Berm Filling

Rs. 12,20,083.56

IV Price Escalation[Approx] Rs.2, 78,41,323.42

V Unpaid 19 & 20 RAR Bills [for Sign

Board, Milleage

Stone, drainage, retaining wall etc.]

Rs.2,88,10,659.00 +

Rs.1,20,83,155.00

Rs. 4,08,93,814.00

VI Total Pending Bill amounts Rs. 23,68,11,589.00

15. Thereafter, the writ petitioner filed a writ petition before the High

Court on or about 23.11.2015 for quashing of the letter dated

27.8.2015. The writ petitioner was informed vide the said letter to

process the bills through laid down channels before DC Contract

and Commander Contract. The letter dated 21.10.2015 was also

challenged which is a reply to the notice under Section 80 of the

Code of Civil Procedure, 1908. A writ of mandamus was prayed for

to pay a sum of Rs.31,57,16,134/- with 18% interest. In reply to

the said writ petition, the assertions made by the writ petitioner


were controverted but also an objection was raised that there was

a clause for arbitration for resolving disputes arising between the

parties, therefore, the writ petitioner should have approached the

designated authority by appointment of an arbitrator.

16. The appellants in their affidavit had pointed out that after completion

of the formation work, the writ petitioner had communicated

expenses of Rs.16,93,51,980/- as against provision of

Rs.16,26,71,039.40. It was asserted that the writ petitioner has

been paid a sum of Rs.42.27 crores as against original cost of

Rs.31.01 crores whereas the contractor has claimed a total sum of

Rs.71.86 crores. The letter dated 29.10.2013 has been issued by

the Headquarters, Border Road Task Force stating that the minimum

distance was to be measured from center line of carriage way

and not from the edge of the roadway. Thus, the entire claim was

based upon imaginary and arbitrary grounds which was enhanced

from time to time.

17. Mr. Nataraj, learned ASG appearing for the appellants, pointed out

that there are serious disputes about the facts in respect of

authenticity of the Joint Final Report and the work done. Therefore,

such disputed question of facts could not have been adjudicated by

the Writ Court as disputed question of facts relating to recovery of

money could not have been entertained thereunder. Reliance has

been placed upon the judgment of this Court reported as Kerala

State Electricity Board & Anr. v. Kurien E. Kalathil & Ors.2

2 (2000) 6 SCC 293


wherein it was held as under:

“10. We find that there is a merit in the first contention of

Mr Raval. Learned counsel has rightly questioned the

maintainability of the writ petition. The interpretation and

implementation of a clause in a contract cannot be the

subject-matter of a writ petition. Whether the contract

envisages actual payment or not is a question of

construction of contract. If a term of a contract is violated,

ordinarily the remedy is not the writ petition under Article

226. We are also unable to agree with the observations of

the High Court that the contractor was seeking enforcement

of a statutory contract. A contract would not become

statutory simply because it is for construction of a public

utility and it has been awarded by a statutory body. We are

also unable to agree with the observation of the High Court

that since the obligations imposed by the contract on the

contracting parties come within the purview of the Contract

Act, that would not make the contract statutory. Clearly, the

High Court fell into an error in coming to the conclusion that

the contract in question was statutory in nature.

11. A statute may expressly or impliedly confer power on a

statutory body to enter into contracts in order to enable it to

discharge its functions. Dispute arising out of the terms of

such contracts or alleged breaches have to be settled by the

ordinary principles of law of contract. The fact that one of

the parties to the agreement is a statutory or public body

will not by itself affect the principles to be applied. The

disputes about the meaning of a covenant in a contract or

its enforceability have to be determined according to the

usual principles of the Contract Act. Every act of a statutory

body need not necessarily involve an exercise of statutory

power. Statutory bodies, like private parties, have power to

contract or deal with property. Such activities may not raise

any issue of public law. In the present case, it has not been

shown how the contract is statutory. The contract between

the parties is in the realm of private law. It is not a statutory

contract. The disputes relating to interpretation of the terms

and conditions of such a contract could not have been

agitated in a petition under Article 226 of the Constitution of

India. That is a matter for adjudication by a civil court or in

arbitration if provided for in the contract. Whether any

amount is due and if so, how much and refusal of the

appellant to pay it is justified or not, are not the matters

which could have been agitated and decided in a writ

petition. The contractor should have relegated to other

remedies.”

18. Mr. Nataraj also placed reliance on the judgment of this Court

reported as Joshi Technologies International Inc v. Union of

India & Ors.3 wherein the following was held:

“55. Law in this aspect has developed through catena of

judgments of this Court and from the reading of these

judgments it would follow that in pure contractual matters

the extraordinary remedy of writ under Article 226 or Article

32 of the Constitution cannot be invoked. However, in a

limited sphere such remedies are available only when the

non-Government contracting party is able to demonstrate

that it is a public law remedy which such party seeks to

invoke, in contradistinction to the private law remedy

simpliciter under the contract. Some of the case law to bring

home this cardinal principle is taken note of hereinafter.

xx xx xx

59. On the basis of these facts, this Court observed that the

aforesaid observations of the High Court relying upon

Ramana Dayaram Shetty case [(1979) 3 SCC 489 : (1979) 2

LLJ 217] were not correct. Thus observed the Court,

speaking through Ratnavel Pandian, J.: (Ajai Pal Singh case

[(1989) 2 SCC 116 : (1989) 1 SCR 743] , SCC pp. 125-26,

paras 21-22)

“21. This finding in our view, is not correct in the light

of the facts and circumstances of this case because in

Ramana Dayaram Shetty case [(1979) 3 SCC 489 :

(1979) 2 LLJ 217] there was no concluded contract as

in this case. Even conceding that the BDA has the

trappings of a State or would be comprehended in

‘other authority’ for the purpose of Article 12 of the

Constitution, while determining price of the

houses/flats constructed by it and the rate of monthly

instalments to be paid, the ‘authority’ or its agent after

entering into the field of ordinary contract acts purely

in its executive capacity. Thereafter the relations are

no longer governed by the constitutional provisions but

by the legally valid contract which determines the

rights and obligations of the parties inter se. In this

sphere, they can only claim rights conferred upon

them by the contract in the absence of any statutory

3 (2015) 7 SCC 728

obligations on the part of the authority (i.e. BDA in this

case) in the said contractual field.

22. There is a line of decisions where the contract

entered into between the State and the persons

aggrieved is non-statutory and purely contractual and

the rights are governed only by the terms of the

contract, no writ or order can be issued under Article

226 of the Constitution of India so as to compel the

authorities to remedy a breach of contract pure and

simple — Radhakrishna Agarwal v. State of Bihar

[(1977) 3 SCC 457], Premji Bhai Parmar v. DDA [(1980)

2 SCC 129] and Divl. Forest Officer v. Bishwanath Tea

Co. Ltd. [(1981) 3 SCC 238 : (1981) 3 SCR 662] ”

xx xx xx

69. The position thus summarised in the aforesaid principles

has to be understood in the context of discussion that

preceded which we have pointed out above. As per this, no

doubt, there is no absolute bar to the maintainability of the

writ petition even in contractual matters or where there are

disputed questions of fact or even when monetary claim is

raised. At the same time, discretion lies with the High Court

which under certain circumstances, it can refuse to exercise.

It also follows that under the following circumstances,

“normally”, the Court would not exercise such a discretion:

69.1. The Court may not examine the issue unless the

action has some public law character attached to it.

69.2. Whenever a particular mode of settlement of dispute

is provided in the contract, the High Court would refuse to

exercise its discretion under Article 226 of the Constitution

and relegate the party to the said mode of settlement,

particularly when settlement of disputes is to be resorted to

through the means of arbitration.

69.3. If there are very serious disputed questions of fact

which are of complex nature and require oral evidence for

their determination.

69.4. Money claims per se particularly arising out of

contractual obligations are normally not to be entertained

except in exceptional circumstances.”

19. It was thus argued that in view of the arbitration clause available to

resolve the disputes, the order of the High Court was unwarranted

and untenable. It was also argued that the High Court in the

impugned order has held that resurvey was not possible as five

monsoons have passed, therefore, the appellants were directed to

approve the DPR and pay the pending bills on the basis of Final

Joint Report.

20. The letter dated 27.8.2015 was issued by the Chief Engineer,

Project Vartak denying the allegations levelled by the writ

petitioner and informing the writ petitioner that the Board of

Officers is being cancelled at his request. It was also pointed out

that the Board of Officers was constituted at the request of the writ

petitioner to resolve the matter. The letter dated 21.10.2015 was

in fact reply to the notice served by the petitioner under Section 80

of Code of Civil Procedure, 1908.

21. Ms. Meenakshi Arora, learned senior counsel for the writ petitioner,

contended that the officer who had written such abovementioned

letter was not the competent authority to write the same. Such

argument was based upon an averment in the memorandum of

appeal. The memorandum of appeal was signed by the panel

counsel and was not supported by any affidavit of an officer of the

appellant. We do not find any merit in the said argument raised.

The letter itself stated that it has been approved by the Competent

Authority. It appears that the decision was taken by the competent

authority but the communication was issued by an officer on behalf

of the competent authority. The basis of Joint Survey Report itself

has been found to be fallacious. This Report appears to be a

friendly act of some of the officers of the appellant, to grant benefit

to the writ petitioner, though even not claimed by the petitioner at

an early stage. The claim of Rs.23,68,11,589.02 in the letter dated

17.6.2014 has swelled into an amount of Rs. 35,51,80,651 as per

the notice under Section 80 of the Code. Therefore, for the

purposes of these proceedings, the communication dated

29.10.2013 cannot be permitted to be disputed by the writ

petitioner.

22. The Board of Officers convened its meeting but the same was

cancelled vide communication dated 8.6.2015. Thus, an attempt

by the appellants to resolve the disputes regarding the

measurements by constituting Board of Officers was scuttled by

the writ petitioner for the reasons best known to him.

23. The High Court has based its order on the ground that after five

monsoons, the final measurements could not be ascertained. If the

final measurements could not be done at the spot, the

contemporary evidence and the measurement books prepared

from time to time could be the basis for determining the liability of

the appellants. The Joint Survey Report is not an admitted

measurement, though some officers might have signed it. The

Report prepared after the completion of work wherein no such work

done is reflected in the measurement book prepared during


execution of work is an attempt to inflate the claim raised by the

writ petitioner. The entire amount claimed by the writ petitioner is

disputed. It has been asserted that the entire payment due as

against the claim of work order had been made, as reflected from

the following table:

I Awarded cost of the work

under the Contract

Rs.31.87 Crores

II Cost of the work already

executed by the department

on the same stretch before the

award of work

Rs.0.86 Cr.

III Cost of the work as reduced in

view of prior departmental

work

Rs.31.01 Crores

IV Amended cost of work under

the Contract

Rs.35.03 Crores

V Contract cost in revised DPR

processed to Ministry of Road,

Transport and Highways

Rs. 42.27 Crores

VI Payment made to the

contractor/respondent herein

inclusive of Rs.3.86 Crores as

per the order dated

18.05.2017 of the Hon'ble

High Court

Rs.42.27 Crores

VII Contractor's claim as per final

bill dated 23.11.2015

Rs. 71. 76 Crores

24. Therefore, the dispute could not be raised by way of a writ petition on the disputed questions of fact. Though, the jurisdiction of the

High Court is wide but in respect of pure contractual matters in the

field of private law, having no statutory flavour, are better

adjudicated upon by the forum agreed to by the parties. The

dispute as to whether the amount is payable or not and/or how

much amount is payable are disputed questions of facts. There is

no admission on the part of the appellants to infer that the amount

stands crystallized. Therefore, in the absence of any acceptance of

Joint Survey Report by the competent authority, no right would

accrue to the writ petitioner only because measurements cannot

be undertaken after passage of time. Maybe, the resurvey cannot

take place but the measurement books of the work executed from

time to time would form a reasonable basis for assessing the

amount due and payable to the writ petitioner, but such process

could be undertaken only by the agreed forum i.e., arbitration and

not by the Writ Court as it does not have the expertise in respect of

measurements or construction of roads.

25. A perusal of the matter shows that collusion of some of the officers

of the appellants with the contractor cannot be ruled out. Such

collusion seems to be the basis of the writ petition filed before the

High Court.

26. In view of the above discussion, we deem it appropriate to allow

the present appeal while dismissing the writ petition filed by the

writ petitioner before the High Court.

.............................................J.

(HEMANT GUPTA)

.............................................J.

(A.S. BOPANNA)

NEW DELHI;

SEPTEMBER 6, 2021.


Print Page

No comments:

Post a Comment