Sunday 19 March 2023

Delhi HC: Arbitrator Can Declare Terms Of Contract Null, Even If No Declaration Is Sought By The Party In Its Pleadings

  It further held that because the rate of interest was left blank in Clause 60.8 (b) in the Appendix to the Bid to which a reference was made in the said clause. It was held to be uncertain and ineffective and therefore void under Section 29 of the Indian Contract Act.  {Para 24}

25. In the case of Oriental Structural Engineers Private Limited Vs. State of Kerala (2021) 6 SCC 150, manner of interpretation of Clause 60.8 of COPA, which is the subject matter of the present Award, came up for consideration. The plea of the rate of interest being left blank was specifically considered and the contention of the respondent was that not specifying the rate of interest and leaving it blank in the Appendix document amounted to a waiver and no interest was payable on any amount. Rejecting this plea, it was held that once there was a clause for levy of interest, merely because the rate of interest was not specified it would not amount to waiver but the Arbitrator, exercising his discretion, could award the interest at any reasonable rate. In the said case, the learned Arbitrator granted simple interest @ 8 % which was upheld by the Apex court.

26. The Arbitral Tribunal interpreted the terms of the contract and while rejecting the claim of the petitioner for compound Interest, it gave various reasons in which the clause providing for interest was also considered and held to be defunct, null and void being incomplete and vague. The objections of the Appellant that there being no pleading seeking clause 60.8 (b) to be declared null and void, the Ld. Arbitrator has made out a 3rd case in itself, is totally not tenable as it was within the domain of the Arbitrator to interpret the terms of the contract. The Tribunal exercised its discretion on the rate of interest to be granted, in absence of an agreement to this effect. The MajorityAward has given a well reasoned Award while granting simple interest.

 IN THE HIGH COURT OF DELHI AT NEW DELHI

Pronounced on: 13th March, 2023

 OMP (COMM.) 283/ 2021

M/S. MODI CONSTRUCTION COMPANY Vs M/S IRCON INTERNATIONAL LIMITED

CORAM:

 MS. JUSTICE NEENA BANSAL KRISHNA

Citation: 2023/DHC/001790

1. In the aforesaid Petitions under Section 34 of the Arbitration &

Conciliation Act, 1996 (hereinafter referred to as the A & C Act, 1996) has

been filed to challenge the Award dated 18.11.2020 with corrections made

on 12.12.2020 passed by the Majority Arbitral Tribunal.

2. The facts in brief are that Government of Andhra Pradesh awarded a

contract for the project „Widening and Strengthening of the Warangal-

Karimnagar-Raiputnam Road (APSH 1)‟ to the respondent. The respondent

in turn divided the project into two parts: first section from Warangal to

Karimnagar (km 06.00 to 66.00) denoted as APSH-1(a) and other from

Karimnagar to Raiputnam (km 164.00 to 219.10) denoted as APSH-1(b).

For the execution of the contract and works connected to the project, the

respondent awarded several contracts to other agencies. The entire work of

APSH-1 (a) was entrusted to the petitioner through two contracts, the

breakup being, the first one for the widening and strengthening of the Road

(excluding Bill No.5 – Bitumen Work & Bill No.8 – Road Furniture) dated 05.05.1998 and the second one for the asphalting work involved dated

29.08.1998. After entering into above two Contract Agreements, execution

of work from both the contracts from km 6.00 to 22.00 was withdrawn from

the petitioner and was given to another agency by a tripartite Agreement

dated 05.08.1999. The petitioner thus, executed work only from km 22.0

onwards.

3. During the course of execution of the two contracts, disputes arose

between the parties. The Contract provided for referral of disputes to a

Disputes Review Board, but it was never constituted by mutual consent.

The matter was referred to a Conciliator who was appointed by the

Respondent vide letter dated 19.08.2003. However, the conciliation

proceedings were terminated by the Conciliator on 29.08.2006. Thereafter,

the Petitioner invoked Arbitration under clause (Sub Clause 67.3, Conditions

of Particular Application) by its letter dated 10.05.2007 and eventually three

Member Arbitral Tribunal was constituted.

4. The parties presented their Statement of Claim and Defence and led

their evidence. The learned Arbitral Tribunal gave a Majority Award and a

Dissenting Award by one Arbitrator dated 18.11.2020 in respect of the

claims. The learned Dissenting Arbitrator awarded Compound Interest

while the Majority Tribunal awarded Simple Interest. The only challenge in

the present petition is grant of Simple Interest by the Majority Tribunal

instead of Compound interest as awarded by the Minority Award.

5. Clause 60.8(b) of the Contract provided for two things; one for

compound interest and other for the rate of interest. The grant of simple

interest by Majority Award has been challenged on the ground that the

finding is perverse since the respondent in its Statement of defence, had only taken an objection to the rate of interest without specifying whether it was to

be compound or simple. When no objection has been raised on behalf of the

respondent that this Clause was null and void as the rate of interest had not

been prescribed, the compound interest should not have been denied merely

because the rate of interest was not mentioned. The Majority Tribunal failed

to consider the severability of the Clause and wrongly held the entire Clause

as void merely because the rate of interest was not specified. In fact, the

correct position of law has been narrated in the Minority Award which must

prevail in the present case and the finding of the Majority Tribunal granting

simple interest, must be rejected.

6. Submissions heard and the written Submissions on behalf of the

Petitioner and Respondent have also been perused.

7. At the outset, it is pertinent to note that in OMP (COMM) 313/2021

the petitioner has raised a claim for the additional cost incurred in extending

bank Guarantees which were illegally withheld against bridging Finances.

The same is not being pressed by the Petitioner and is hereby dismissed.

8. The parties had admittedly entered into two Contract Agreements

dated 05.05.1998 and 29.08.1998 for the work of widening and

strengthening of Warangal- Raiputnam Road (Warangal-KarimNagar

Section km 6.00 to 66.00) and for the work of widening and strengthening of

Warangal- Karimnagar Road APSH-I-A Asphalt work respectively. The

disputes had arisen between the parties and the disputes were referred to the

Arbitral Tribunal comprising of three members. Two Awards were passed,

one by the Majority Arbitral Tribunal awarding interest @ 9% Simple

Interest p.a. The Dissenting learned Arbitrator in the minority Award

granted interest @ 9% to be Compounded monthly instead of Simple

Interest per annum. The sole challenge in both the petitions is denial of

compound interest on the pre-Award amount by the Majority Award.

9. The claimant/appellant in terms of sub clause 60.8 of COPA had

claimed interest on the various claimed amount for three periods namely: pre

reference, pendente lite and post award. The entire controversy is on the

interpretation of Sub clause 60.8(b) of COPA which provided that:

“(b)In the event of failure of the Employer to make payment

within times stated, the Employer shall pay to the Contractor

interest compounded monthly at the rate(s) stated in the

Appendix to bid upon all sums unpaid from the date upon which

the same should have been paid in the currencies in which the

payments are due. The provisions of this Sub-Clause are

without prejudice to the Contractor‟s entitlement under Clause

69 or otherwise."

10. Dissenting learned Arbitrator in minority Award observed that the

provision of payment of interest compounded monthly was specifically

inbuilt in the contract conditions, which was applicable to all payments till

the final payment/settlement of all the disputes and till the Final Certificate

was issued by the Respondent. The interest payable was liable to be

compounded monthly as agreed between the parties which could not be

altered by the Arbitral Tribunal. Though in the said Sub Clause, the rate of

interest was to be as per Annexure to Bid in which the rate of interest was

left as blank, but the fundamental principle of interpretation of contract is

that the provisions of the contract should be read harmoniously and such

part of the Contract which can be segregated must be given effect to in terms

of Section 23 (3) of the Contract Act, 1872. Even though the rate of interest

was not provided that could not invalidate the manner of calculation of the

interest and therefore, while agreeing to grant the interest @ 9 % the

Dissenting Arbitrator directed that the interest must be compounded

monthly.

11. The Majority Tribunal however, held that when in the Clause

providing for interest, the rate of interest was left blank and was not

specified, the entire clause could not be operated, suffered from uncertainty

and was ineffective. Thus, the entire clause became defunct ipso facto. The

observations of Majority Tribunal invalidating Sub- Clause 60.8 of COPA

are as under:

“[139] Having concluded that the Tribunal is empowered

under the Contract to award interest claimed along with a

Claim, the issue to be addressed is as to whether interest,

compounded monthly or simple interest, be awarded.

The case laws relied upon by the Claimant cannot be disputed;

it is well settled that payment of compound interest is in order,

subject to the provisions of the Contract (emphasis given).

Provisions of the Contract, therefore, now need to be examined

by the Tribunal. Sub- Clause 60.8(b) requires that the rate of

interest will be that prescribed in the Appendix to Bid. It is

undisputed that the said Appendix does not prescribe interest;

in fact, it does not even mention it. Without the rate of interest,

the said Clause cannot be operated, suffers from uncertainty

and is ineffective. The said Clause is, therefore, void under

Section 29 of The Indian Contract Act (emphasis added).

The Claimant‟s argument that notwithstanding the absence of

mention of a rate of interest in the Appendix, prevailing/current

prime leading rates must be considered as the Contract between

the Parties is a commercial contract has no legal basis, as also

his submission that the rate of interest to be adopted in the

Contract was to be as per actual and accordingly the Parties

willingly did not mention any specific rate in the Appendix to


Bid. The Arbitral Tribunal cannot amend a contract and

introduce new conditions and provisions.

Further, the Claimant‟s argument of comparing and seeking

support from the stipulations relating to Bridging Finance in

the Contract Agreement is misplaced. The stipulation relating to

Bridging Finance prescribed interest to be charged „as per

actual‟; and as what constitutes actual was determined by the

Conciliator in his Award. The stipulation relating to interest

payable was thus not totally absent and, in any event, settled by

a due process prescribed under the Act.

The Tribunal concludes that the contention of the Claimant

that he is entitled to payment of compound interest on a

monthly basis under the said Clause as untenable. In other

words, the Claimant cannot seek any shelter under this Sub-

Clause and the Respondent’s objection, sustains.”

12. In the present case, the only controversy is whether the interest @ 9 %

that has been awarded by the learned Arbitrator is to be calculated as simple

interest as directed by the Majority decision or it should be compounded

monthly as held in the dissenting opinion of the learned Arbitrator.

13. This controversy needs to be examined in the light of the limited

scope of interference which the Court has under Section 34 of the A & C

Act, 1996. To question the legality of the decision of the minority or the

majority opinion, we need to first test if the grounds of challenge to the

Award are met by the test laid down by the Apex court in various cases. In

ONGC v. Saw Pipes (2003) 5 SCC 705, the Apex Court had observed that if

the Arbitral Tribunal has committed mere error of fact or law in reaching its

conclusion on the disputed question submitted to it for adjudication then the

court would have no jurisdiction to interfere with the award. However, this

would depend upon reference made to the arbitrator: (a) if there is a general


reference for deciding the contractual dispute between the parties and if the

award is based on erroneous legal proposition, the court could interfere; (b)

in a case of reasoned award, the court can set aside the same if it is on the

face of it, erroneous on the proposition of law or its application; and (c) if a

specific question of law is submitted to the arbitrator, erroneous decision in

point of law does not make the award bad, so as to permit its being set aside,

unless the court is satisfied that the arbitrator had proceeded illegally.

14. Comprehensive judicial literature on the scope of interference on the

ground of Public Policy under Section 34 was postulated in Associate

Builders v. DDA (2015) 3 SCC 49. The Apex Court placed reliance on the

judgment of ONGC v. Saw Pipes (supra) to determine the contours of Public

Policy wherein an award can be set aside if it is violative of the „fundamental

policy of Indian law', 'the interest of India', 'Justice or morality' or leads to a

'Patent Illegality'.

15. The ground of 'patent illegality' is applied when there is a

contravention of the substantive law of India, the Arbitration Act or the rules

applicable to the substance of the dispute. In Hindustan Zinc Limited vs

Friends Coal Carbonisation (2006) 4 SCC 445, The Hon'ble Apex Court

referred to the principles laid down in Saw Pipes (supra) and clarified that it

is open to the court to consider whether an Award is against the specific

terms of contract, and if so, interfere with it on the ground that it is patently

illegal and opposed to the public policy of India.

16. Similarly in Ssangyong Engineering and Construction Co. Ltd v.

N.H.A.I (2019) 15 SCC 131 and Anglo American Metallurgical Coal Pty

Ltd v. MMTC Ltd 2020 SCC OnLine SC 1030 the Apex Court observed the

circumstances that would attract a “patent illegality” appearing on the face


of the award are if: (i) the arbitrator fails to give reasons in the award in

violation of Section 31(3) of the A&C Act; (ii) the arbitrator has taken an

impossible view in construing the contract; (iii) the arbitrator transgresses

his jurisdiction, and (iv) if the arbitrator has made a perverse finding based

on no evidence, overlooking vital evidence or based on documents taken up

as evidence without giving proper notice to the parties.

17. The controversy raised by way of present petitions may now be

considered in the light of above stated scope of interference under S.34 of

the A&C Act, 1996 on the ground of “patent illegality”.

18. Indisputably, the ld. Arbitrator is empowered to grant interest while

adjudicating a money claim. While examining the Claim to interest it must

be understood that the underlying principle guiding award of interest is that

it is essentially compensatory in nature as explained by the Constitution

Bench of the Apex Court in Irrigation Department, State of Orissa vs. G.C.

Roy (1992) 1 SCC 508, wherein it observed that a person deprived of the

use of money to which he is legitimately entitled, has a right to be

compensated for the deprivation which may be called interest, compensation

or damages. This basic consideration is as much valid for the period for

which the dispute is pending before the Arbitrator as it is for the period prior

to or before the reference was made to the Arbitrator. This is also the

principle incorporated in Section 34 of the Code of Civil Procedure, 1908

and there is no reason or principle to hold otherwise in the cases referred for

arbitration.

19. The Apex court in the case of State of Haryana and Others v. S.L.

Arora and Company, (2010) 3 SCC 690, that according to Section 31 of the

A & C Act, 1996 in the pre-award period, interest has to be awarded as


specified in the Contract while in the absence of contract, the interest may be

granted by the Arbitral Tribunal as per its own discretion. Further, if the

Contract provides for compounding of the interest or provides for payment

of interest upon interest or for interest payable on the principle to be treated

as part of the principle for the purpose of calculation of interest during the

subsequent period, the Arbitral Tribunal should give effect to it. However, if

the Award is challenged under Section 34 of the A & C Act, 1996 and if the

Court finds that the interest awarded is in conflict with or violative of the

public policy of India, it may set aside that part of the Award.

20. The difference between clause (a) and clause (b) of Section 31 (7) of

the Act, 1996 was explained thus:

(i) Clause (a) relates to pre-award period and the Contract binds

and prevails in regard to grant of interest during this period.

(ii) Clause (b) gives the discretion to the Arbitral Tribunal to

award interest for the post-award period but it is not subject

to any contract and the Arbitral Tribunal may grant interest

in exercise of its discretion.

21. Now, coming to the facts of the present case, the Majority Tribunal,

while granting simple interest observed that Clause 60.8 of COPA

(Conditions of Particular Application) was not the only clause providing for

the payment of interest on interim payments and final statement. Various

clauses/stipulations contained in the Contract Agreement are required to be

looked into which laid down the procedure, including time-frame, for raising

claims. It was observed by the Tribunal that the Claimant had not led any

evidence to establish that the procedure under such sub-clauses was followed

by it.


22. It was further noted that the monthly statements for claiming the

interim payments were governed by sub-clause 60.1 of the Conditions of

Particular Application and vide item (k), the contractor is required to include

“any other sum, expressed in applicable currency or currencies, to which

the Contractor may be entitled under the Contract or otherwise”. The

Tribunal noted from the documents placed before it that the claim for

interest @ 18% p.a. was first made by the claimant vide letter dated

27.01.2001 (Exhibit R123, Document RR3); the demand was for “all

withheld payments and on other claims from the date of submission” but

without any quantification. There was no mention of the interest being on a

monthly compounded basis. Subsequently, vide Letter dated 25.03.2001

(Exhibit R8) total 19 claims were made and the interest claimed was @ 18 %

p.a without any quantification. The only document where compound interest

was claimed is in the calculation of the claimed amounts filed along with the

amended Claims wherein the calculation of interest was on the formula of

compound interest. In the entire pleadings, however, no claim for compound

interest was made.

23. Further, in the conciliation proceedings before the Conciliator, the

claimant again included payment of interest @ 18 % p.a on his claim

amounts, past and pendent lite. The Conciliation proceedings however

remained inconclusive. The claimant then submitted a Draft Final Statement

Part B but again neither the rate of interest nor the amount was indicated. It

got established that there were various claims that were made from time to

time and the rate of interest claimed at 18 % p.a, without any quantification

or qualification of it being compounded monthly. The provisions of sub

Clause 53.1 and 53.3 were thus, never followed.


24. It further held that because the rate of interest was left blank in Clause

60.8 (b) in the Appendix to the Bid to which a reference was made in the

said clause. It was held to be uncertain and ineffective and therefore void

under Section 29 of the Indian Contract Act. Further, the claimant claimed

interest free “mobilization Advance” as a percentage of the Contract value.

The second type of advance to which the claimant was entitled was

Machinery Advance which was also free of interest. The respondent, in turn,

was entitled to interest free advances for the above two from the Principal

Employer under the Main Contract and consequently these two types of

advances were in the nature of pass on and therefore, not relevant to help

arrive at a reasonable rate of interest by the Tribunal. The third type of

advance was Bridging Finance for which the interest was claimed @ 15.5 %

on the principle of reciprocity of rate of interest by stating that the same is

the rate that it had to pay its bankers in the overdraft maintained by it. The

Respondent submitted that the interest rate was calculated on a monthly

compounding basis by taking an arbitrary rate of 15.5% as the same was not

indicated in the contract or adopted for any transaction between the parties.

The Tribunal noted that the petitioner‟s claim of interest @ 15.5% by

comparing and seeking support from stipulations related to Bridging Finance

in the Contract Agreements was misplaced. The Tribunal concluded that the

claim of the Petitioner of compounded interest on a monthly basis was

untenable for this reason as well.

25. In the case of Oriental Structural Engineers Private Limited Vs. State of Kerala (2021) 6 SCC 150, manner of interpretation of Clause 60.8 of COPA, which is the subject matter of the present Award, came up for consideration. The plea of the rate of interest being left blank was specifically considered and the contention of the respondent was that not specifying the rate of interest and leaving it blank in the Appendix document amounted to a waiver and no interest was payable on any amount. Rejecting this plea, it was held that once there was a clause for levy of interest, merely because the rate of interest was not specified it would not amount to waiver but the Arbitrator, exercising his discretion, could award the interest at any

reasonable rate. In the said case, the learned Arbitrator granted simple interest @ 8 % which was upheld by the Apex court.

26. The Arbitral Tribunal interpreted the terms of the contract and while rejecting the claim of the petitioner for compound Interest, it gave various reasons in which the clause providing for interest was also considered and held to be defunct, null and void being incomplete and vague. The objections of the Appellant that there being no pleading seeking clause 60.8 (b) to be declared null and void, the Ld. Arbitrator has made out a 3rd case in itself, is

totally not tenable as it was within the domain of the Arbitrator to interpret the terms of the contract. The Tribunal exercised its discretion on the rate of interest to be granted, in absence of an agreement to this effect. The MajorityAward has given a well reasoned Award while granting simple interest.

27. Merely because an alternative view as taken by minority Tribunal had

taken, was also possible, does not get encompassed in patent illegality. For

this, reference be made to Dyna Technologies (P) Ltd vs Crompton Greaves

Ltd. (2019) 20 SCC 1 wherein the Apex Court observed that arbitral awards

should not be interfered with unless the court comes to a conclusion that the

perversity of the award goes to the root of the matter and there is no

alternative interpretation that can be possibly taken which may sustain the

award. Where two views are possible, the court cannot interfere in the plausible view taken by the arbitrator for which reasoning is provided. If the

court comes to the conclusion that such interpretation was reasonably

possible then it is not usually required for it to examine the merits of the

interpretation provided by the arbitrator.

28. Similarly, the Supreme Court in Indian Oil Corporation Ltd. v. Shree

Ganesh Petroleum, Rajgurunagar (2022) 4 SCC 463 drew a distinction

between failure to act in terms of a contract and an erroneous interpretation

of the terms of a contract and observed that the Court does not sit in appeal

over the award made by an Arbitral Tribunal. The Court does not ordinarily

interfere with interpretation of a contractual provision that is made by the

Arbitral Tribunal, unless such interpretation is patently unreasonable or

perverse. Where a contractual provision is ambiguous or is capable of being

interpreted in more ways than one, the Court cannot interfere with the

arbitral award only because the Court is of the opinion that another possible

interpretation would have been a better one.

29. The Apex Court has reiterated in SAIL v. Gupta Brother Steel Tubes

Ltd., (2009) 10 SCC 63; Sumitomo Heavy Industries Ltd. v. ONGC Ltd.,

(2010) 11 SCC 296 and in Rashtriya Ispat Nigam Limited v. Dewan Chand

Ram Saran (2012) 5 SCC 306, that if the conclusion of the arbitrator is

based on a possible view of the matter and if the view taken by arbitrator is

possible one, the court is not expected to interfere with the award.

30. Likewise, in the matter of MSK Projects India (JV) Limited v. State of

Rajasthan (2011) 10 SCC 573, the Supreme Court held that an error in the

construction of the contract cannot be held to be without jurisdiction.

31. As the scope of interference of this Court under Section 34 of A & C

Act, 1996 is very limited and the court must restrict itself to the above principles, this court does not find any infirmity in the Award regarding grant of simple interest by the Tribunal. The Arbitrator has interpreted the terms of contract and the petitioner‟s claim of interest was based on the

interpretation of the term of contract and clause 60.8 (b) of the COPA in

particular and applied the principles of law in the impugned award. As

established by the above mentioned principles, this court does not sit in

appeal over the Award made by an Arbitral Tribunal and cannot substitute

its own reasoning for that of the Arbitrators, especially when the same is

reasonable. This Court does not find merit in the claim of compound interest

raised by the Petitioner herein.

32. The two Petitions are thereby dismissed.

(NEENA BANSAL KRISHNA)


MARCH 13, 2023


Print Page

No comments:

Post a Comment