What remedy is available to student if results of revaluation are delayed?

There is no merit in the submission made on behalf of the
University that the petitioners and the other students like them are
provided with the facility of revaluation as an additional facility and
there  is no right in them to seek revaluation.  We do not find any force
in the submission made on behalf of the University that there is no right
to seek revaluation.   We find on a reading of Direction No.5 of 2004
that the students are entitled to make applications seeking revaluation
of their answer­sheets. The very fact that the petitioners were declared
unsuccessful initially as per the results declared on 16/06/2015 and are
declared successful after revaluation, clearly shows that it was the fault
of the University in not awarding appropriate marks to the petitioners at
the first valuation. The fact that the petitioners were initially declared
unsuccessful and are declared successful after revaluation clearly shows
that the facility is deserved.  We have witnessed that sometimes some
worthy   students   are   either   declared   unsuccessful   or   are   awarded
extremely low marks in the initial valuation and after revaluation they
are declared successful and their marks are increased significantly.  At
least, in case of such students, it cannot be said that revaluation is an
additional facility which the University has granted to the students due
to its generosity. 

8. We do not find any force in the submission made on behalf
of the University that the revaluation results were declared within a
period of 65 days.  We are not inclined to reckon the period from the
date of making of the application for revaluation as the results were
declared   in   the   case   of   the   petitioners   on   16/06/2015   and   the
declaration of the revaluation results was on 05/10/2015.  This clearly
shows that the results of the petitioners were declared after a period of
110 days from the date of declaration of the results.  We find that there
is a gross delay in the declaration of the results of the petitioners in the
instant  case. The submission made on  behalf of the  University  that
about   135   to   140   days   are   required   for   completing   the   process   of
revaluation is ridiculous. If this is accepted, the results of the students
would not be declared till the next supplementary examination.  Also,
the students would not be entitled to admission in the subsequent year
of the same course or to a new course if the last date for submission of
the mark­sheet for appearing at the examination of the advanced course
or   the   next   year   of   the   same   course   is   25th  of   September.     The
revaluation facility would be illusory. The students may not know till
the beginning of the supplementary examination whether they would or
would not be required to appear at the supplementary examination, if
the revaluation results are declared in 135 to 140 days. 

9. Also,   we   find   that   the   principle   of  lex   non   cogit   ad
impossibilia would apply to the facts of this case.  The petitioners cannot
be asked to do something that is impossible and is not within the reach
of the petitioners.   The petitioners had applied for revaluation and it
was   the   duty   of   the   respondent   No.2­University   to   reevaluate   the
answer­sheets  within a reasonable time.  If the University was at fault
in not declaring the revaluation results of the petitioners before the
stipulated date, i.e. 25/09/2015, the petitioners cannotbenon­suited for
not submitting the mark­sheets before that date.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
WRIT PETITION NO. 6293    OF    2015
 Ms. Sneha Fulchand Hargude, 
...VERSUS... 
 Joint   Director   of   Technical   Education,

­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­­
      CORAM : SMT. VASANTI A. NAIK &
A.S.CHANDURKAR, JJ.
      DATED  : 01.03.2016
Citation: 2016(3) ALLMR577