Saturday 9 April 2022

Whether one party can withhold performance bank guarantee if it has acknowledged due performance of contract?

  In view of the above, the Arbitral Tribunal had rightly directed

refund of the amount recovered by BSNL from invocation of the

Performance Bank Guarantee in question. There is no principle in law whereby BSNL could be permitted to retain the Performance Security after it had acknowledged due performance of the Contract. {Para 19}

IN THE HIGH COURT OF DELHI AT NEW DELHI

 Judgment delivered on: 28.03.2022

 O.M.P. (COMM) 431/2019 & I.A. 14326/2019

BHARAT SANCHAR NIGAM LIMITED  Vs TERACOM LIMITED 

CORAM

HON’BLE MR JUSTICE VIBHU BAKHRU


1. The petitioner (hereafter ‘BSNL’) has filed the present petition

under Section 34 of the Arbitration and Conciliation Act, 1996

(hereafter ‘the A&C Act’) impugning an arbitral award dated

28.06.2019 delivered by an Arbitral Tribunal constituted by a Sole

Arbitrator (hereafter the ‘Arbitral Tribunal’).

2. On 15.07.2010, BSNL had issued a Notice Inviting Tenders

(NIT), being no. MM/NWP-CDMA/072010/000393, for purchase of

9,80,000 units of Integrated Fixed Wireless Terminal Devices (IFWT),

CDMA Terminals. The respondent (hereafter ‘Teracom’) participated

in the said tender and was declared as the successful bidder.

3. Accordingly, BSNL issued an Advance Purchase Order

(hereafter ‘APO’) on 02.12.2010, in favour of Teracom for purchase of


3,75,000 units of WLL CDMA 2000 1x IFWTs. In terms of the APO,

on 18.12.2010, Teracom furnished a Performance Bank Guarantee

bearing number 21641LG025810 for an amount of ₹2,12,97,000/-,

which was valid for a period of three years.

4. On 02.02.2011, BSNL placed a Purchase Order bearing P.O no.

CE/PO/009/2010-2011 (hereafter the ‘Contract’) for procurement of

3,75,000 units of WLL CDMA 2000 1x IFWTs (L1, PKG-1) from the

respondent, for a total value of ₹ 42,59,29,581/-.

5. In terms of Article 11 of the Contract, the respondent was entitled

to 80% of the total payment on supply of the IFWT equipment at site,

and the balance 20% payment after one year of the equipment’s

satisfactory performance and on signing of the Annual Maintenance

Contract (AMC) with the respective State Telecom Circles under BSNL

along with submission of the Performance Bank Guarantee.

6. Admittedly, there was delay in payment of 80% of the total

payment that was due under the Contract. By its letter dated 09.04.2012,

Teracom informed BSNL that even though it had provided complete

supply of the IFWT equipment, several State Telecom Circles of BSNL

had failed to release 80% of the payment due to it.

7. Correspondence was exchanged between Teracom and various

State Telecom Circles from May, 2014 till December, 2016. Teracom

states that most State Telecom Circles had thereafter, released the

payments, which were due to Teracom; however, an amount of

₹1,52,91,987/- remained outstanding.


8. The Performance Bank Guarantee dated 18.12.2010 was initially

for a term of three years but Teracom had extended the same from time

to time, at the instance of BSNL. It was last extended till 30.09.2017.

On 01.08.2017, BSNL, once again, called upon Teracom to extend the

Performance Bank Guarantee till 30.09.2018. Teracom resisted the said

request. Thereafter, by its letter dated 10.08.2017, Teracom stated it had

met all its obligations under the Contract and requested that the

Performance Bank Guarantee be released. BSNL did not do so and

invoked the Performance Bank Guarantee on 09.01.2018.

9. In view of the disputes between the parties, Teracom issued a

notice dated 27.01.2018 to the Chairman and Managing Director,

BSNL, invoking the Arbitration Agreement and seeking reference of

the disputes to arbitration.

10. Before the Arbitral Tribunal, Teracom raised the following

claims:

“Claim no. 1:- Entitlement to refund an amount of Rs.

21,297,000.00 which is equivalent to PBG by the claimant

in terms of APO dated 02-12-2010.

Claim no. 2:- Payment towards outstanding dues of

Rs.1.53 Crores towards the bills raised by the claimant.

Claim no. 3:- Interest at the rate of 18% per annum on the

claims of the claimant till the date of passing the award at

the first instance. Further to treat the amount as Principal

Sum awarded and grant further interest at the rate of 18%

per annum till the amount is paid to the claimant in total.

Claim no. 4:- Litigation cost.


Claim no. 5:- Payment of Rs. 1 crore by the respondent for

breach of contract, harassment, mental agony and damages

Claim no. 6:- Any further reliefs for the claimant as found

entitled.”

11. BSNL filed its Statement of Defence, however, it did not raise

any Counter-claims.

12. By the impugned award, the Arbitral Tribunal has awarded an

amount of ₹2,12,97,000/- in favor of Teracom, which was the amount

recovered by BSNL by encashing the Performance Bank Guarantee

(Claim No. 1). Further, the Arbitral Tribunal awarded an amount of

₹1,37,97,207/- as the balance amount due to Teracom under the

Contract, from various State Telecom Circles (Claim No. 2). The

Arbitral Tribunal also awarded interest at the rate of 16% per annum

from 15.08.2019 till realization of the total amount of ₹3,50,94,207/-

(₹2,12,97,000/- plus ₹1,37,97,207/-), if it was not paid on or before that

date.

Submissions

13. Ms Narula, learned counsel appearing for BSNL, has assailed the

impugned award, essentially, on two fronts. First, she submitted that the

Arbitral Tribunal had grossly erred in directing refund of the amount

recovered by BSNL by encashment of the Performance Bank

Guarantee. She submitted that in terms of the Contract, BSNL was

entitled to forfeit the Performance Bank Guarantee and since Teracom

had not extended the Performance Bank Guarantee as was required,

BSNL had encashed the same. She contended that once the Performance

Bank Guarantee was encashed, there was no obligation on the part of

BSNL to refund the same and the amount stood forfeited.

14. Second, she submitted that the Arbitral Tribunal had grossly

erred in rejecting BSNL’s claim for a set off. She submitted that there

was ample evidence on record to show that BSNL had levied penalty

albeit, in respect of another purchase order and in terms of the Contract,

BSNL was entitled to retain the amounts payable to Teracom in respect

of the supplies made under the Contract, on account of dues owed by it

to BSNL.

Reasons and Conclusion

15. The contention that BSNL was entitled to forfeit the

Performance Bank Guarantee even though Teracom had performed the Contract, is bereft of any merit. Teracom had submitted the

Performance Bank Guarantee, which was initially for a term of three

years with effect from 18.12.2010. Thus, the Performance Bank

Guarantee expired on 17.12.2013. However, BSNL had insisted that the

same be extended as at the material time; the Contract had not been fully

performed. The Arbitral Tribunal noted that the Performance Bank

Guarantee was successively extended eight times. The last extension

was up to 30.09.2017. However, since the Performance Bank Guarantee was not extended thereafter, BSNL had invoked the same. It is

important to note that the Performance Bank Guarantee was invoked

not because BSNL had claimed that any amount was due to it or that

Teracom had failed to perform the Contract; it was done solely for the


reason that the No Claim Certificates (NCCs) had not been issued by

various Circles and therefore, BSNL was required to be secured for due

performance of the Contract in question. There was no occasion for

BSNL to forfeit any amount recovered against the Performance Bank

Guarantee because BSNL had not made any claim regarding failure on

the part of Teracom to perform its obligations under the Contract.

16. The contention that BSNL is entitled to forfeit the amount on

encashment of the Bank Guarantee, apart from being unmerited, runs

contrary to the defence set up by BSNL in its Statement of Defence.

Paragraph 7 of its Statement of Defence filed before the Arbitral

Tribunal is relevant and set out below:

“7. Further, the bank guarantee was a security given

by the Claimant to ensure that the goods were supplied

to the Respondent in terms of the Purchase Order dated

02.02.2011. The successful delivery of the goods could

only be ascertained once the Respondent received NCC/

TOC from the respective Circles. Since the Respondent

had not received the required NCC/ TOC from all its

Circles, the bank guarantee had to be kept alive.

However, the Claimant failed to keep the bank guarantee

alive and therefore in December, 2017 when the Bank

refused to extend the bank guarantee any further and

asked the Respondent to encash it instead. Therefore, the

Respondent was constrained to encash the bank

guarantee only because the Bank refused to extend the

same. It is pertinent to mention that the same has been

encashed in terms of the Performance Bank Guarantee

itself. As mentioned above, even though the same has

been encashed, it is kept as a security deposit and the

amount shall be released to the Claimant once it


completes its contractual obligations towards the

Respondent.”

17. It is clear from the above that it was BSNL’s contention that it

was holding the money recovered from invoking the Performance Bank

Guarantee as a security deposit, which would be refunded to Teracom

after the NCCs were received from various Telecom Circles.

18. The Arbitral Tribunal had noted that the witness examined by

BSNL [Mr Sanjesh Kumar Kaim, AGM (SE), BSNL] had affirmed in

his affidavit dated 04.01.2019 that BSNL had received the Takeover

Certificates / No Claim Certificates (TOC/NCC) from all the concerned

twenty-four State Telecom Circles of BSNL. The Arbitral Tribunal also

noted that BSNL had clarified by a clarification dated 03.06.2019, that

the last NCC was received from the Kolkata Circle on 20.10.2018. The

aforesaid findings of the Arbitral Tribunal are not disputed.

19. In view of the above, the Arbitral Tribunal had rightly directed

refund of the amount recovered by BSNL from invocation of the

Performance Bank Guarantee in question. There is no principle in law

whereby BSNL could be permitted to retain the Performance Security

after it had acknowledged due performance of the Contract.

20. The contention that the impugned award is vitiated by patent

illegality as the Arbitral Tribunal had rejected BSNL’s claim for a set

off, is also unmerited. There is no dispute that in terms of the Contract

between the parties, BSNL was entitled to claim a set off of any amount

due to it against any amount payable to Teracom under the Contract.


However, in this case, there was no such effective claim for various

reasons as noted hereafter.

21. It is relevant to note that the issue of set off was raised in respect

of two State Telecom Circles of BSNL – the Kerala Circle and the

Madhya Pradesh Circle. In the case of the Kerala Circle, it was

contended on behalf of BSNL that it was entitled to adjust penalty of a

sum of ₹54,19,728/-, which was imposed in respect of PO No.

CE/PO/020/2007-2008 dated 26.02.2008. In respect of the Madhya

Pradesh Circle, BSNL contended that it was entitled to adjust penalty

of a sum of ₹2,60,87,800/- imposed in connection with PO No.

CE/PO/006/2003-04 dated 01.09.2003.

22. Teracom had countered the aforesaid contentions. The Arbitral

Tribunal had examined BSNL’s contention and rejected the claim,

essentially, on four grounds. First, it found that there was no such claim

for a set off made in the Statement of Defence filed by BSNL. Second,

it found that in respect of the Kerala Circle, BSNL had claimed levy of

penalty by four letters (letters dated 03.03.2016, 05.04.2016,

21.07.2016 and 09.01.2017); however, perusal of the said letters did not

indicate that BSNL had made a case for a set off. Third, that the issue

of levy of penalty was disputed and the same had not crystalised. And

fourth, the Arbitral Tribunal noted that BSNL’s claim for imposition of

levy of penalty appeared to be, ex facie, barred by limitation.

23. Concededly, BSNL had not raised the claim for a set off in its

Statement of Defence. Ms Narula had submitted that no such defence


could have been raised as the claim for a set off had arisen after the

Statement of Defence/Reply to the Statement of Claims, was filed.

Undisputedly, in order to claim a set off, it was necessary for BSNL to

have established that an ascertained sum of money was due and payable

to it. And, since no such defence was raised, this Court is unable to

fault the decision of the Arbitral Tribunal to reject the said claim.

24. The contention that the claim for a set off had arisen after filing

of the Statement of Defence also appears to be erroneous considering

that it was BSNL’s case that the set off pertains to a Purchase Order

dated 26.02.2008, in respect of the Kerala Circle and, a Purchase Order

dated 01.09.2003, in the case of the Madhya Pradesh Circle. However,

even assuming that any claim for a set off was crystalised after filing of

the Statement of Defence, it was open for BSNL to have sought an

amendment to its Statement of Defence. However, admittedly, no such

amendment was sought.

25. In view of the above, this Court finds no ground to fault the

impugned award.

26. The petition is unmerited and accordingly, dismissed. The

pending application is also disposed of.

VIBHU BAKHRU, J