However, the issue is not limited to interpretation of Clause 18.1 of the Concession Agreement, solely on which the impugned award, essentially, rests. The interpretation of Clause 18.4 of the Concession Agreement is also vital to the controversy in the present case. The petitioner had relied on Clause 18.4 of the Concession Agreement and had contended that in terms of the said clause, any additional civil works were specifically excluded from the purview of Article XVIII of the Concession Agreement. Undisputedly, construction of additional lanes and toll booths entailed civil works and Clause 18.4 of the Concession Agreement expressly provided that “maintenance shall not include the extension of any existing pavement, bridges, structures and other civil works unless part of the project”. Clause 18.4 of the Concession Agreement, thus, clarified that extension of any structure or other civil works would not be included as part of maintenance. The written submissions filed by the petitioner before the Arbitral Tribunal indicates that the petitioner had canvassed the said clause and specifically clarified that the construction of additional lanes over and above as specified under the Concession Agreement, is excluded from the scope of maintenance. A plain reading of the impugned award indicates that the Arbitral Tribunal had not considered Clause 18.4 of the Concession Agreement while interpreting the question whether construction of the additional lanes fall within the scope of Operation and Maintenance obligations of the petitioner. {Para 49}
50. Mr. Chandra had submitted that Clause 18.4 of the Concession Agreement would not exclude construction of additional lanes as Clause 18.1 of the Concession Agreement has an overriding effect to include the same within the scope of the project. This contention is not persuasive. However, more importantly, it is clear that the Arbitral Tribunal has not considered this contention even though it was urged before the Arbitral Tribunal. Undeniably, Clause 18.1 of the Concession Agreement could not have been interpreted in isolation. It was also required to be examined in the context of the other clauses of the Concession Agreement - including Clause 18.4 of Concession Agreement, Clause 2.1 of the Concession Agreement, which defined the scope of the contract and Clause 2 of Schedule C of the Concession Agreement, which described the specifications of a toll plaza, were also required to be interpreted.
51. In view of the above, there is merit in the petitioner's contention that since one of the principal contentions advanced by the petitioner regarding interpretation of Article XVIII of the Concession Agreement has not been considered and the impugned award rests substantially on the interpretation of a sub-clause of Article XVIII of the Concession Agreement; the award must be construed to be unreasoned.
52. Section 31(3) of the A&C Act requires that an arbitral award must state reasons upon which it has been based. The said requirement must be read in a meaningful manner. In an adversarial system of litigation, the reasons for a decision must necessarily take into account the relevant rival contentions. Thus, the question whether construction of additional lanes and toll booths fall within the scope of the Concession Agreement was required to be addressed in the light of the contentions advanced by both parties. However, the Arbitral Tribunal has completely ignored the petitioner's contention regarding the interpretation of Clause 18.4 of the Concession Agreement.
53. Justice (Retired) Devinder Gupta has, in his opinion, considered all the relevant clauses of the Concession Agreement including Clause 18.4 of the Concession Agreement and concluded that the scope of work under the Concession Agreement did not include construction of additional lanes at the toll plazas. This Court concurs with the said view.
54. In the aforesaid context, this Court is of the view that the impugned award is contrary to the expressed terms of the contract as it ignores Clause 18.4 of the Concession Agreement, which expressly provides that extension of pavements or ‘other civil works’ would not be included as a part of maintenance unless such construction is a part of the project. There is no clause in the Concession Agreement, which specified construction of additional toll lanes as a part of the project.
55. In view of the above, the impugned award is set aside. The petitioner is at liberty to seek a reference of the disputes to arbitration.
In the High Court of Delhi at New Delhi
(Before Vibhu Bakhru, J.)
GVK Jaipur Expressway Private Limited Vs National Highway Authority of India
O.M.P. (COMM) 377/2020
Decided on October 29, 2021
Citation: 2021 SCC OnLine Del 4851
Print Page