It is true that in submitting its tender accompanied by a cheque of the Union Bank of India and not of the State Bank the clause no. 6 of the tender notice was not obeyed literally, but the question is as to whether the said non- compliance deprived the Diesel Locomotive Works of the authority to accept the bid. As a matter of general proposition it cannot be held that an authority inviting tenders is bound to give effect to every term mentioned in the notice in meticulous detail, and is not entitled to waive even a technical irregularity of little or no significance. The requirements in a tender notice can be classified into two categories-those which lay down the essential conditions of eligibility and the others which are merely ancillary or subsidiary with the main object to be achieved by the condition. In the first case the authority issuing the tender may be required to enforce them rigidly. In the other cases it must be open to the authority to deviate from and not to insist upon the strict literal compliance of the condition in appropriate cases. This aspect was examined by this Court in GJ Fernandez v. State of Karnataka 7 Ors., [1990] 2 SCC 488 a case dealing with tenders. Although not in an entirely identical situation as the present one, the observations in the judgment support our view. The High Court has, in the impugned decision, relied upon Ramana Dayaram Shetty v. International Airport Authority of India & Ors., [1979] 3 SCC 489 but has failed to appreciate that the reported case belonged to the first category where the strict compliance of the condition could be insisted upon. The authority in that case, by not insisting upon the requirement in the tender notice which was an essential condition of eligibility, bestowed a favour on one of the bidders, which amounted to illegal discrimination. The judgment indicates that the Court closely examined the nature of the condition which had been relaxed and its impact before answering the question whether it could have validly condoned the shortcoming in the tender in question. This part of the judgment demonstrates the difference between the two categories of the conditions discussed above. However it remains to be seen as to which of the two clauses, the present case belongs.
7. The nature of payment by a certified cheque was considered by this Court in Sita Ram Jhunjhunwala v. Bombay Bullion Association Ltd. & Anr., [1965] 35 Company Cases
526. Several objections were taken there in support of the plea that the necessary condition in regard to payment was not satisfied and in that context this Court quoted the observations from the judgment in an English decision (vide Spargo's case: 1873 L.R. & Ch. App. 407) that it is a general rule of law that in every case where a transaction resolves itself into paying money by A to B and then handing it back again by B to A, if the parties meet together and agree to set one demand against the other, they need not go through the form and ceremony of handing the money backwards and forwards. This Court applied that the observations to a transaction requiring payment by one to another. The High Court's decisions in B.D. Yadav's case and T.V. Subhadra Amma's case are also illustrations where literal compliance of every term of the tender notice was not insisted upon.
8. In the instant case the certified cheque of the Union Bank of India drawn on is own branch must be treated as sufficient for the purpose of achieving the object of the condition and the Tender Committee took the abundant caution by a further verification from the bank. In this situation it is not correct to hold that the Diesel Locomotive Works had no authority to waive the technical literal compliance of clause 6, specially when it was in its interest of not to reject the said bid which was the highest.
Supreme Court of India
Poddar Steel Corporation vs Ganesh Engineering Works And ... on 6 May, 1991
Equivalent citations: 1991 AIR 1579, 1991 SCR (2) 696
BENCH:
SHARMA, L.M. (J)
PUNCHHI, M.M.
CITATION:
1991 AIR 1579 1991 SCR (2) 696
1991 SCC (3) 273 JT 1991 (2) 577
1991 SCALE (1)928