As against the above submissions, it was contended on behalf of the respondent in the said decision that even if the existence of the main contract is under dispute, the Court is concerned only with the arbitration agreement, i.e. the arbitration clause and that when once such a Clause is very much present, that would by itself result in the matter being referable for arbitration. In fact, in the said case, the Clause relating to arbitration was found in Clause No.18.1 which provided for an attempt to resolve the dispute, controversy or difference through mutual consultation and if it is not resolved through mutual consultation within 30 days after commencement of discussion, then the parties may refer the dispute, controversy or difference for resolution to an Arbitral Tribunal.
Dealing with the said Clause and the arguments raised on behalf of the respective parties, the law has been laid down as under in paragraphs 82 and 83 which are to the following effect:
"82. Further, the arbitration agreement contained in Clauses 18.1 to 18.3 of IPLA is very widely worded and would include all the disputes, controversies or differences concerning the legal relationship between the parties. It would include the disputes arising in respect of the IPLA with regard to its validity, interpretation, construction, performance, enforcement or its alleged breach. Whilst interpreting the arbitration agreement and/or the arbitration clause, the court must be conscious of the overarching policy of least intervention by courts or judicial authorities in matters covered by the Indian Arbitration Act, 1996. In view of the aforesaid, it is not possible for us to accept the submission of Mr Nariman that the arbitration agreement will perish as the IPLA has not been finalised. This is also because the arbitration clause (agreement) is independent of the underlying contract i.e. the IPLA containing the arbitration clause. Section 16 provides that the arbitration [pic]clause forming part of a contract shall be treated as an agreement independent of such a contract.
83. The concept of separability of the arbitration clause/agreement from the underlying contract is a necessity to ensure that the intention of the parties to resolve the disputes by arbitration does not evaporate into thin air with every challenge to the legality, validity, finality or breach of the underlying contract. The Indian Arbitration Act, 1996, as noticed above, under Section 16 accepts the concept that the main contract and the arbitration agreement form two independent contracts. Commercial rights and obligations are contained in the underlying, substantive, or the main contract. It is followed by a second contract, which expresses the agreement and the intention of the parties to resolve the disputes relating to the underlying contract through arbitration. A remedy is elected by parties outside the normal civil court remedy. It is true that support of the national courts would be required to ensure the success of arbitration, but this would not detract from the legitimacy or independence of the collateral arbitration agreement, even if it is contained in a contract, which is claimed to be void or voidable or unconcluded by one of the parties."
Supreme Court of India
Ashapura Mine-Chem Ltd vs Gujarat Mineral Devlopment ... on 16 April, 2015
Bench: Fakkir Mohamed Kalifulla, Shiva Kirti Singh
Reportable
APPEAL NO. 3702 OF 2015
(@ SLP (C) NO.1963 of 2014)
Citation:AIR 2015 SC(SUPP)1153