Showing posts with label genuine pre-estimate of loss. Show all posts
Showing posts with label genuine pre-estimate of loss. Show all posts

Saturday, 22 December 2018

Whether a plea can be taken in argument in appeal in absence of pleading?

As far as argument of discrimination is concerned, there are no foundational facts in support of this argument. No such plea was taken either before the AFT or in the instant appeal. Only with the additional documents, communication dated February 6, 2014 is enclosed which the Appellant has received under the Right to Information Act, 2005 in respect of Surg Cdr Haresh Maini. On the basis of this document, oral submission was made at the time of arguments. It is not known as to under what circumstances recovery of proportionate cost was made in his case. Moreover, in the absence of pleadings, the Respondents did not have any opportunity to explain the same. Therefore, such a plea cannot be allowed in the facts of this case.

IN THE SUPREME COURT OF INDIA

Civil Appeal No. 1491 of 2018 (Arising out of Diary No. 35797 of 2017)

Decided On: 01.02.2018

Ashwini Kumar Handa Vs. Union of India (UOI) and Ors.

Hon'ble Judges/Coram:
A.K. Sikri and Ashok Bhushan, JJ.

Citation: 2018(6) MHLJ 25
Print Page

Thursday, 18 October 2018

Whether court should grant compensation for breach of contract if there is no loss to other side?

 In my opinion there is also a legal issue on the basis of which this appeal has to be allowed and the suit for recovery filed by the appellant/plaintiff has to be decreed. This is because of the provisions of Sections 73 and 74 of the Indian Contract Act, 1872. In law merely because there is a breach of contract such breach is not actionable unless because of the breach loss is caused to the aggrieved party. There can be forfeiture of an amount paid under a contract only when the aggrieved party is caused loss. Two relevant judgments in this regard are the judgments of the Constitution Bench of the Supreme Court in the case of Fateh Chand Vs. Balkishan Dass AIR 1963 SC 1405 and the recent judgment of the Supreme Court in the case of Kailash Nath Associates Vs. Delhi Development Authority and Another, (2015) 4 SCC 136. The relevant paras in the judgment in the case of Kailash Nath Associates (supra) are paras 34, 43 and 43.1 to 43.7 and these paras read as under:-
"34. In Fateh Chand v. Balkishan Das, this Court held: "The section is clearly an attempt to eliminate the somewhat elaborate refinements made under the English common law in distinguishing between stipulations providing for payment of liquidated damages andstipulations in the nature of penalty. Under the common law a genuine pre-estimate of damages by mutual agreement is regarded as a stipulation naming liquidated damages and binding between the parties: a stipulation in a contract in terrorem is a penalty and the Court refuses to enforce it, awarding to the aggrieved party only reasonable compensation. The Indian Legislature has sought to cut across the web of rules and presumptions under the English common law, by enacting a uniform principle applicable to all stipulations naming amounts to be paid in case of breach, and stipulations by way of penalty.....
* * * Section 74 of the Indian Contract Act deals with the measure of damages in two classes of cases (i) where the contract names a sum to be paid in case of breach and (ii) where the contract contains any other stipulation by way of penalty. We are in the present case not concerned to decide whether a covenant of forfeiture of deposit for due performance of a contract falls within the first class. The measure of damages in the case of breach of a stipulation by way of penalty is by Section 74 reasonable compensation not exceeding the penalty stipulated for. In assessing damages the Court has, subject to the limit of the penalty stipulated, jurisdiction to award such compensation as it deems reasonable having regard to all the circumstances of the case. Jurisdiction of the Court to award compensation in case of breach of contract is unqualified except as to the maximum stipulated; but compensation has to be reasonable, and that imposes upon the Court duty to award compensation according to settled principles. The section undoubtedly says that the aggrieved party is entitled to receive compensation from the party who has broken the contract, whether or not actual damage or loss is proved to have been caused by the breach. Thereby it merely dispenses with proof of "actual loss or damages"; it does not justify the award of compensation when in consequence of the breach no legal injury at all has resulted, because compensation for breach of contract can be awarded to make good loss or damage which naturally arose in the usual course of things, or which the parties knew when they made the contract, to be likely to result from the breach.(At page 526, 527) * * *Section 74 declares the law as to liability upon breach of contract where compensation is by agreement of the parties pre-determined, or where there is a stipulation by way of penalty. But the application of the enactment is not restricted to cases where the aggrieved party claims relief as a Plaintiff. The section does not confer a special benefit upon any party; it merely declares the law that notwithstanding any term in the contract predetermining damages or providing for forfeiture of any property by way of penalty, the court will award to the party aggrieved only reasonable compensation not exceeding the amount named or penalty stipulated. The jurisdiction of the court is not determined by the accidental circumstance of the party in default being a Plaintiff or a Defendant in a suit. Use of the expression "to receive from the party who has broken the contract" does not predicate that the jurisdiction of the court to adjust amounts which have been paid by the party in default cannot be exercised in dealing with the claim of the party complaining of breach of contract. The court has to adjudge in every case reasonable compensation to which the Plaintiff is entitled from the Defendant on breach of the contract. Such compensation has to be ascertained having regard to the conditions existing on the date of the breach."
xxxxx xxxxx xxxxx
43. On a conspectus of the above authorities, the law on compensation for breach of contract Under Section 74 can be stated to be as follows:
43.1. Where a sum is named in a contract as a liquidated amount payable by way of damages, the party complaining of a breach can receive as reasonable compensation such liquidated amount only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the Court. In other cases, where a sum is named in a contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated. Similarly, in cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded not exceeding the penalty so stated. In both cases, the liquidated amount or penalty is the upper limit beyond which the Court cannot grant reasonable compensation.
43.2. Reasonable compensation will be fixed on well known principles that are applicable to the law of contract, which are to be found inter alia in Section 73 of the Contract Act.
43.3. Since Section 74 awards reasonable compensation for damage or loss caused by a breach of contract, damage or loss caused is a sine qua non for the applicability of the Section.
43.4. The Section applies whether a person is a Plaintiff or a Defendant in a suit.
43.5. The sum spoken of may already be paid or be payable in future.
43.6. The expression "whether or not actual damage or loss is proved to have been caused thereby" means that where it is possible to prove actual damage or loss, such proof is not dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount named in the contract, if a genuine pre-estimate of damage or loss, can be awarded. 43.7. Section 74 will apply to cases of forfeiture of earnest money under a contract. Where, however, forfeiture takes place under the terms and conditions of a public auction before agreement is reached, Section 74 would have no application."
(underlining added)
8. In the present case as is seen from the admitted facts on record that the respondent/defendant neither as per its written statement nor as per its evidence led, ever pleaded and proved that any loss has been caused to the respondent/defendant on account of the failure by the appellant/plaintiff to take dealership of the respondent/defendant. Therefore even assuming that there is some breach of contract on the part of the appellant/plaintiff, yet since no loss has been caused to the respondent/defendant which is pleaded and proved, therefore in accordance with the ratio of the judgments of the Supreme Court in the cases of Fateh Chand (supra) and Kailash Nath Associates (supra), the respondent/defendant could not have forfeited the total amount of Rs.6,25,000/- deposited by the appellant/plaintiff with the respondent/defendant.
Delhi High Court
M/S Grover Tankers Investment vs M/S Otc Exchange Of India on 15 October, 2018

CORAM:
HON'BLE MR. JUSTICE VALMIKI
Print Page

Sunday, 19 August 2018

Whether person aggrieved by breach of contract is required to prove that actual loss or damage was suffered by him?

 It can thus be seen that, in every case of breach of a contract, the person aggrieved by the breach, is not required to prove the actual loss or damage suffered by him, before he can claim a decree and the Court is competent to award reasonable compensation in case of breach, even if, no actual damage is "proved", to have been suffered in consequence of the breach of contract. But the expression "whether or not actual damage or loss is proved to have been caused thereby", as appearing in the said section is intended to cover different types of contracts, which come before the Courts. In case of some contracts, it may be impossible for the Courts to asses compensation, arising from such breach. In such cases, the section dispenses with the proof of such loss or damage and the Court can grant the compensation in terms of the liquidated damages, if the sum named by the parties is regarded as a genuine pre-estimate of such loss. 
IN THE HIGH COURT OF BOMBAY AT GOA

Appeal Under Arbitration Act No. 8 of 2016

Decided On: 10.04.2018

Titagarh Wagons Limited Vs. Chowgule and Company Private Limited
Print Page

Saturday, 10 September 2016

Whether S 74 of contract Act is applicable when contract has been broken?


It must, however, be pointed out that in cases where a public
auction is held, forfeiture of earnest money may take place even
before an agreement is reached, as DDA is to accept the bid only after
the earnest money is paid. In the present case, under the terms and
conditions of auction, the highest bid (along with which earnest
money has to be paid) may well have been rejected. In such cases,
Section 74 may not be attracted on its plain language because it
applies only “when a contract has been broken”.
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 193 OF 2015

M/s. Kailash Nath Associates V Delhi Development Authority & Anr. .
Dated:January 09, 2015.
Citation:AIR 2015 SC(Supp)780
Print Page

How to ascertain reasonable compensation for loss caused by breach of contract?

On the second question, i.e whether the defendant was entitled to
forfeit the amount of ` 1 crore, the single judge analyzed the terms of the
agreement (Ex. PW-1/2) especially Clause 2 which was the forfeiture
condition. The defendant’s argument that all the amounts paid by the
plaintiff constituted earnest money, was rejected:
“Nowhere in the agreement is it stipulated that payment made after
the execution of the agreement would also be covered by the forfeiture
clause. The Earnest Money/Part Payment of Rs. 1,01,00,000/ - as
stipulated in clause 1 would alone be liable to be forfeited.”
Thereafter, the single judge recorded the following finding:
“73. The Defendant is thus entitled to forfeit the amount of Rs.
1,01,00,000/- and is liable to refund the balance amount of Rs.
1,60,00,000/-. I have already held that the Plaintiffs have not been
able to prove the payment of Rs.5,00,000/-. Since the Plaintiffs have
been held liable for committing the breach of the contract, in my view
ends of justice would be met if the Defendant were directed to refund
the balance amount with interest only @ 8% per annum from the date
of filing of the suit.”
29. In such cases, where a party alleges that a forfeiture clause constitutes
a genuine pre-estimate of damages, two considerations have to be weighed 
by the court. One, the task of scrutinizing whether the condition is in reality
one that parties envisioned to be a genuine pre-estimate of damage likely to
be suffered is to be viewed in the context of some proof of “reasonable
damage” that Section 74 of the Contract Act mandates; two, that there might
be cases where the likely damage is one which cannot be estimated with
precision, given the nature of the contract, in which event, the court might
consider if the amount stipulated was one foreseen as reasonable
compensation payable to the aggrieved party without proof of damage or
loss.
30. Kailash Nath Associates v. Delhi Development Authority (2015) 4
SCC 136 is a recent authority on the question of liquidated damages
specified in a contract. The Supreme Court considered the law in Fateh
Chand v Balkishan Dass AIR 1963 SC 1405and several other decisions, and
held as follows:
"The law laid down by a Bench of 5 Judges in Fateh Chand's case is
that all stipulations naming amounts to be paid in case of breach
would be covered by Section 74. This is because Section 74 cuts
across the rules of the English Common Law by enacting a uniform
principle that would apply to all amounts to be paid in case of breach,
whether they are in the nature of penalty or otherwise…
43. On a conspectus of the above authorities, the law on
compensation for breach of contract under Section 74 can be stated to
be as follows:
1. Where a sum is named in a contract as a liquidated amount
payable by way of damages, the party complaining of a breach can
receive as reasonable compensation such liquidated amount only if it
is a genuine pre-estimate of damages fixed by both parties and found
to be such by the Court. In other cases, where a sum is named in a
contract as a liquidated amount payable by way of damages, only
reasonable compensation can be awarded not exceeding the amount 
so stated. Similarly, in cases where the amount fixed is in the nature
of penalty, only reasonable compensation can be awarded not
exceeding the penalty so stated. In both cases, the liquidated amount
or penalty is the upper limit beyond which the Court cannot grant
reasonable compensation.
2. Reasonable compensation will be fixed on well known principles
that are applicable to the law of contract, which are to be found inter
alia in Section 73 of the Contract Act.
3. Since Section 74 awards reasonable compensation for damage or
loss caused by a breach of contract, damage or loss caused is sine
qua non for the applicability of the Section.
4. The Section applies whether a person is a plaintiff or a defendant in
a suit.
5. The sum spoken of may already be paid or be payable in future.
6. The expression "whether or not actual damage or loss is proved to
have been caused thereby" means that where it is possible to prove
actual damage or loss, such proof is not dispensed with. It is only in
cases where damage or loss is difficult or impossible to prove that the
liquidated amount named in the contract, if a genuine pre-estimate of
damage or loss, can be awarded.
7. Section 74 will apply to cases of forfeiture of earnest money under
a contract. Where, however, forfeiture takes place under the terms
and conditions of a public auction before agreement is reached,
Section 74 would have no application."
In Fateh Chand (supra), the Supreme Court had articulated the applicable
principle as follows:
“In all cases, therefore, where there is a stipulation in the nature of
penalty for forfeiture of an amount deposited pursuant to the terms of
contract which expressly provides for forfeiture, the court has
jurisdiction to award such sum only as it considers reasonable, but
not exceeding the amount specified in the contract as liable to
forfeiture.”
31. In the present case, the defendant did not show how it was put to loss
or damage. The record clearly establishes that though the attachment order
was vacated sometime in 2007, the Bank was pursuing the matter. It is not
disputed that the pendency of the Bank’s claim in DRT and the likely cloud
on the property was never pointed out to the plaintiff. What is more, the
defendant did not even reveal that an attachment order was issued in 2009.
The plaintiff virtually stumbled upon that fact, as it were. It is doubtful
whether the defendant would have been able to convey title for the amount
agreed, either to the plaintiff or to anyone else, had the reality been
disclosed. Having regard to this conduct, even though the plaintiff is held
disentitled to a decree for specific performance, this court holds that the
defendant cannot claim “reasonable compensation”. Besides, no evidence of
any kind to show that he was put to loss was led. As a result, it is held that
the forfeiture of the amount of `One crore was not justified. Although the
plaintiff sought refund repeatedly his conduct in insisting that the contract
was nevertheless enforceable and the sale deed had to be executed to some
extent disentitles him to interest from October, 2008. However, the record is
clear that from May, 2009 (after he filed a police complaint seeking refund)
he did not intend to go through with the contract; this court has also
recorded that he did not prove his readiness and willingness. In these
circumstances, in the interests of justice, it would be appropriate to direct the
defendant to refund the sum of `One crore to the plaintiff and also pay 9%
interest on that amount, with effect from the date of filing of the suit, till
date of payment.
IN THE HIGH COURT OF DELHI AT NEW DELHI

PRONOUNCED ON: 25.05.2016
RFA (OS) 160/2014, CM APPL.20644/2014

SURJIT SINGH BHATIA Vs  TEJ RAJ SINGH GOEL (GOEL) .

CORAM:
HON'BLE MR. JUSTICE S. RAVINDRA BHAT
HON'BLE MS. JUSTICE DEEPA SHARMA
Print Page

Friday, 10 April 2015

When court is entitled to grant reasonable compensation in case of breach of contract?




“64. It is apparent from the aforesaid
reasoning recorded by the Arbitral
Tribunal that it failed to consider Sections
73 and 74 of the Indian Contract Act and
the ratio laid down in Fateh Chand case
wherein it is specifically held that
jurisdiction of the court to award
compensation in case of breach of
contract is unqualified except as to the
maximum stipulated; and compensation
has to be reasonable. Under Section 73,
when a contract has been broken, the
party who suffers by such breach is
entitled to receive compensation for any
loss caused to him which the parties
knew when they made the contract to be
likely to result from the breach of it. This
section is to be read with Section 74,
which deals with penalty stipulated in
the contract, inter alia (relevant for the
present case) provides that when a
contract has been broken, if a sum is
named in the contract as the amount to
be paid in case of such breach, the party
complaining of breach is entitled,
whether or not actual loss is proved to
have been caused, thereby to receive
from the party who has broken the
contract reasonable compensation not
exceeding the amount so named. Section
74 emphasizes that in case of breach of
contract, the party complaining of the
breach is entitled to receive reasonable
compensation whether or not actual loss
is proved to have been caused by such
breach. Therefore, the emphasis is on
reasonable
compensation.
If
the
compensation named in the contract is
by way of penalty, consideration would
be different and the party is only entitled
to reasonable compensation for the loss
suffered. But if the compensation named
in the contract for such breach is
 genuine pre-estimate of losswhich the
parties knew when they made the
contract to be likely to result from the
breach of it, there is no question of
proving such loss or such party is not
required to lead evidence to prove actual
loss suffered by him. Burden is on the
other party to lead evidence for proving
that no loss is likely to occur by such
breach. 

REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS...1440-1441 OF 2015
(ARISING OUT OF SLP (C) NOS.35365-35366 OF 2012)
M/S. CONSTRUCTION & DESIGN SERVICES
...APPELLANT
VERSUS
DELHI DEVELOPMENT AUTHORITY
Dated;FEBRUARY 4, 2015
Print Page