Principal Sum Adjudged and Three Stages of Interest Under Section 34 CPC

 In money decrees, one of the most important questions is: what exactly is the principal sum adjudged, and how is interest calculated before the suit, during the pendency of the suit, and after the decree. Under Section 34 of the Code of Civil Procedure, this distinction is crucial because the court does not treat all kinds of interest in the same manner.

For district judge interview purposes, the concept should be understood in three parts: first, the meaning of principal sum adjudged; second, the three stages of interest; and third, the leading case law explaining the doctrine.

Meaning of principal sum adjudged

Print Page

Thursday, 5 October 2017

WHETHER ARBITRATOR CAN AWARD PENDENTE LITE INTEREST WHEN SPECIFIC PROVISION IN CONTRACT BARS PAYMENT OF INTEREST?

In Union of India vs. Bright Power Projects (India) Private Limited (2015) 9 SCC 695, a three-Judge Bench of this Court, after referring to the provisions of Section 31(7)(a) of the 1996 Act, held that when the terms of the agreement had prohibited award of interest, the Arbitrator could not award interest for the pendente lite period. It has been held thus:
“10. Thus, it had been specifically understood between the parties that no interest was to be paid on the earnest money, security deposit and the amount payable to the contractor under the contract. So far as payment of interest on government securities, which had been deposited by the respondent contractor with the appellant is concerned, it was specifically stated that the said amount was to be returned to the contractor along with interest accrued thereon, but so far as payment of interest on the amount payable to the contractor under the contract was concerned, there was a specific term that no interest was to be paid thereon.
11. When parties to the contract had agreed to the fact that interest would not be awarded on the amount payable to the contractor under the contract, in our opinion, they were bound by their understanding. Having once agreed that the contractor would not claim any interest on the amount to be paid under the contract, he could not have claimed interest either before a civil court or before an Arbitral Tribunal.” Therefore, it is clear that the appellant is not entitled for any interest on the amount awarded by the Arbitral Tribunal.
Reportable
Supreme Court of India
Chittaranjan Maity vs Union Of India on 3 October, 2017
Author: S Nazeer
       CIVIL APPELLATE JURSIDCITON

      CIVIL APPEAL NOS. 15545-15546 OF 2017
    (Arising out of SLP (C) Nos.39038-39039 of 2012)


                      
Print Page

Sunday, 3 April 2016

Whether arbitrator can grant interest pendente lite if it is specifically barred by contract?

 The decision in Madnani Construction Corporation (supra) has
followed decision in Engineers-De-Space-Age (supra). Same is also
required to be diluted to the extent that express stipulation under contract
may debar the Arbitrator from awarding interest pendente lite. Grant of
pendente lite interest may depend upon several factors such as
phraseology used in the agreement, clauses conferring power relating to
arbitration, nature of claim and dispute referred to Arbitrator and on what
items power to award interest has been taken away and for which period.
24. Thus, our answer to the reference is that if contract expressly bars
award of interest pendente lite, the same cannot be awarded by the
Arbitrator. We also make it clear that the bar to award interest on delayed
payment by itself will not be readily inferred as express bar to award
interest pendente lite by the Arbitral Tribunal, as ouster of power of
Arbitrator has to be considered on various relevant aspects referred to in
the decisions of this Court, it would be for the Division Bench to consider
the case on merits.
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
SPECIAL LEAVE PETITION [C] No.11114/2009
Union of India … Petitioner
Vs.
M/s. Ambica Construction … Respondent
(With SLP [C] No.17219/2009]
Dated;March 16, 2016