Coming now to the facts of the case at hand, we
find that wordings of Clause 62 of the contract in
question with which we are concerned is identical to
that of Clause 18 of Union of India (DGS&D) (supra).
Clause 62 of GCC provides for determination of
contract owing to default of contractor. The relevant
portion of Clause 62 reads as under:
“The amounts thus to be forfeited or
recovered may be deducted from any
moneys then due or which at any time
thereafter may become due to the Contractor
by the Railway under this or any other
contract or otherwise.”
42) On perusal of the record of the case, we find that
firstly, arbitration proceedings in relation to the
contract dated 22.08.2005 are still pending. Secondly,
the sum claimed by the respondents from the
appellant does not relate to the contract for which the
Bank Guarantee had been furnished but it relates to
another contract dated 22.08.2005 for which no bank
guarantee had been furnished. Thirdly, the sum
claimed by the respondents from the appellant is in
the nature of damages, which is not yet adjudicated
upon in arbitration proceedings. Fourthly, the sum
claimed is neither a sum due in praesenti nor a sum
payable. In other words, the sum claimed by the
respondents is neither an admitted sum and nor a
sum which stood adjudicated by any Court of law in
any judicial proceedings but it is a disputed sum and
lastly, the Bank Guarantee in question being in the
nature of a performance guarantee furnished for
execution work of contract dated 14.07.2006 (Anand
Vihar works) and the work having been completed to
the satisfaction of the respondents, they had no right
to encash the Bank Guarantee.
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.4814 OF 2016
(ARISING OUT OF SLP(C) No. 27052 of 2012)
M/s Gangotri Enterprises Ltd.
V
Union of India & Ors.
Dated:May 05, 2016.
Print Page
find that wordings of Clause 62 of the contract in
question with which we are concerned is identical to
that of Clause 18 of Union of India (DGS&D) (supra).
Clause 62 of GCC provides for determination of
contract owing to default of contractor. The relevant
portion of Clause 62 reads as under:
“The amounts thus to be forfeited or
recovered may be deducted from any
moneys then due or which at any time
thereafter may become due to the Contractor
by the Railway under this or any other
contract or otherwise.”
42) On perusal of the record of the case, we find that
firstly, arbitration proceedings in relation to the
contract dated 22.08.2005 are still pending. Secondly,
the sum claimed by the respondents from the
appellant does not relate to the contract for which the
Bank Guarantee had been furnished but it relates to
another contract dated 22.08.2005 for which no bank
guarantee had been furnished. Thirdly, the sum
claimed by the respondents from the appellant is in
the nature of damages, which is not yet adjudicated
upon in arbitration proceedings. Fourthly, the sum
claimed is neither a sum due in praesenti nor a sum
payable. In other words, the sum claimed by the
respondents is neither an admitted sum and nor a
sum which stood adjudicated by any Court of law in
any judicial proceedings but it is a disputed sum and
lastly, the Bank Guarantee in question being in the
nature of a performance guarantee furnished for
execution work of contract dated 14.07.2006 (Anand
Vihar works) and the work having been completed to
the satisfaction of the respondents, they had no right
to encash the Bank Guarantee.
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.4814 OF 2016
(ARISING OUT OF SLP(C) No. 27052 of 2012)
M/s Gangotri Enterprises Ltd.
V
Union of India & Ors.
Dated:May 05, 2016.
Citation:(2016) 11 SCC 720

