Mr. Raheja's contention that HPCL was not required to either plead or prove any loss is difficult to accept. In Kailash Nath Associates v. Delhi Development Authority (supra), the Supreme Court had referred to Section 74 of the Indian Contract Act, 1872 and had held as under:—
“43. On a conspectus of the above authorities, the law on compensation for breach of contract under Section 74 can be stated to be as follows:
43.1. Where a sum is named in a contract as a liquidated amount payable by way of damages, the party complaining of a breach can receive as reasonable compensation such liquidated amount only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the court. In other cases, where a sum is named in a contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated. Similarly, in cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded not exceeding the penalty so stated. In both cases, the liquidated amount or penalty is the upper limit beyond which the court cannot grant reasonable compensation.
43.2. Reasonable compensation will be fixed on well-known principles that are applicable to the law of contract, which are to be found inter alia in Section 73 of the Contract Act.
43.3. Since Section 74 awards reasonable compensation for damage or loss caused by a breach of contract, damage or loss caused is a sine qua non for the applicability of the section.
43.4. The section applies whether a person is a plaintiff or a defendant in a suit.
43.5. The sum spoken of may already be paid or be payable in future.
43.6. The expression “whether or not actual damage or loss is proved to have been caused thereby” means that where it is possible to prove actual damage or loss, such proof is not dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount named in the contract, if a genuine pre-estimate of damage or loss, can be awarded.
43.7. Section 74 will apply to cases of forfeiture of earnest money under a contract. Where, however, forfeiture takes place under the terms and conditions of a public auction before agreement is reached, Section 74 would have no application.” {Para 52}
53. HPCL had neither pleaded that it was not feasible to establish the loss nor had led any material to establish that it had suffered loss on account of non-supply of ethanol by DSM. There is also no pleading to the effect that ethanol was otherwise not readily available or available at a price higher than as agreed between DSM and HPCL. DSM's contention that HPCL had failed to establish any loss was contested on an erroneous premise that HPCL was not required to establish the same.
54. In the given circumstances, this Court is of the view that the award of Rs. 88,14,785/- in favour of HPCL, is not sustainable.
In the High Court of Delhi at New Delhi
(Before Vibhu Bakhru, J.)
O.M.P. (COMM) 164/2020 and I.A. No. 2870/2015
Hindustan Petroleum Corporation Ltd. Vs Dhampur Sugar Mills Ltd.
O.M.P. (COMM) 164/2020, I.A. No. 2870/2015 and O.M.P. (COMM) 190/2020
Decided on January 6, 2022
Citation: 2022 SCC OnLine Del 42
Print Page